2010-01-05 Joint CC School Board MinutesMINUTES OF THE SPECIAL JOINT CITY COUNCIL
AND BOARD OF EDUCATION MEETING
TUESDAY- - JANUARY 5, 2010- -7:00 P.M.
Mayor Johnson convened the Joint Meeting at 7:10 p.m.
ROLL CALL - Present: Councilmembers deHaan, Gilmore, Matarrese, L. Tam
and Mayor Johnson; and School Board Members
Jensen, McMahon, Spencer, N. Tam and President
Mooney - 10.
Absent: None.
AGENDA ITEM
(10 -001 CC /BOE) Joint Executive Presentation on Alameda Point Development Initiative
Process, Contents of Initiative, Chronology of Process, Executive Summary, and
Questions and Answers.
The Interim City Manager, Planning Services Manager, Redevelopment Manager, Public
Works Director, and School Superintendent gave a Power Point presentation.
Councilmember L. Tam stated the goal of the election report is to inform the electorate;
inconsistencies should be explained to prevent voter confusion; the City and the developer
have to negotiate the cost of public benefits in the Disposition and Development
Agreement (DDA); the Interim City Manager has indicated public benefits would total $371
million; the initiative includes a $200 million cap; requested that the developer explain the
difference in cost.
Pat Keliher, SunCal Alameda Point Project Manager, stated a business plan was submitted
to the City in December 2008; all the things discussed tonight are consistent with said
plan; SunCal does not agree with the analysis; the analysis should have referred back to
the business plan in order to truly understand costs; the City's report assumes $48 million
for on site roads that are included in the master infrastructure costs in the business plan
and are not part of the public benefits; $103 million in transit improvement soft costs are in
separate sections in the business plan and are not included in the public benefits; the
challenge is the analysis was done by people not privy to those documents [business
plan]; the analysis cannot be done in a vacuum.
Councilmember L. Tam inquired whether the expectation is that the $200 million cap
identified as the hard cost will cover all public benefits infrastructure identified in the
initiative, such as the library, roads and sports facilities.
Mr. Keliher responded in the affirmative; stated SunCal wrote a letter saying that they
Special Joint Meeting
Alameda City Council and 1
Board of Education
January 5, 2010
would be willing to lift the cap; SunCal wants to build the benefits; SunCal believes costs
will be less than $200 million and estimates the cost to be around $170 million; the
discrepancy is tremendous; the City included $4 million for the Sea Plane Lagoon
bulkhead, which is a completely separate budget item.
Councilmember L. Tam stated page 16 of the election report has the definition of the City's
fiscal neutrality policy; the policy explicitly calls for the use of Tax Increment (TI) funding in
the redevelopment area in order to ensure that the new development pays for itself;
November 2009 City correspondence confirms fiscal neutrality; there is confusion over the
2% tax cap, which covers the hospital and school taxes; requested that the developer
clarify why the cap is in the initiative and its effects on the City's operating budget.
Mr. Keliher stated the shortfall that the project has to pick up is about 0.13 %; assuming
Alameda's ad valorem is 1.1 %, 1.23% would ensure all of the fiscal impacts on the City
would be taken care of; the cap was put at 2% because the project is underwritten at 1.8 %,
which is consistent with the business plan; the model only assesses residential, not
commercial; SunCal feels that the market will not accept anything above 2 %; the fiscal
impact analysis done by the City indicated that above 2% is not needed.
In response to Councilmember L. Tam's inquiry about the Bayport community facilities
district, the Public Works Director stated the [Bayport] Maintenance Assessment District
covers public infrastructure and includes costs for emergency services.
Councilmember L. Tam inquired whether emergency service costs are for the Fire
Department, to which the Public Works Director responded costs are for Police or Fire.
Councilmember L. Tam stated ballot arguments reference a $500 million shortfall; inquired
how the amount was derived.
The Interim City Manager responded staff couldn't answer questions on ballot argument
material.
Councilmember Gilmore stated public benefits are supposed to be $371 million; adding the
$52 million in net exactions and subtracting the $200 million cap leaves a $223 million
shortfall if her math is correct.
The Interim City Manager stated Councilmember Gilmore's math is correct as it relates to
the shortfall on capital.
Councilmember L. Tam inquired whether $103 million in soft costs is included.
The Interim City Manager responded the amounts shown on the presentation slides are
what staff believes to be the present value project costs; stated that she is not clear
whether Mr. Keliher is referring to the joint pro forma or another document which is in
Special Joint Meeting
Alameda City Council and 2
Board of Education
January 5, 2010
negotiation; the City's view is the costs are $371 million.
The Public Works Director stated staff relied on the language in the ballot measure; Exhibit
4 in Exhibit F of the initiative lists very general public benefits, including on site and off site
traffic and transit improvements; SunCal is stating that streets within the development itself
should not be included; however, the language does not conclude that [streets within the
development are excluded]; subdivision streets, as well as soft costs, are included based
on the language in the initiative.
Councilmember L. Tam stated the election report refers to the development of a
Transportation Demand Management (TDM) plan; inquired how the TDM plan that SunCal
developed was incorporated in the City's analysis and model.
The Public Works Director responded staff used what is in the initiative, which does not
include a specific TDM program; stated staff worked with consultants to develop a TDM
program that makes sense for the type of mixed use development proposed; staff could
have done modeling if the initiative spelled out the TDM program; staff is concerned that
the caps may not have sufficient funds for public benefits and on going maintenance of
public infrastructure.
In response to Mayor Johnson's inquiry regarding SunCal's estimate of the TDM program,
the Public Works Director stated there is nothing in the initiative.
Mayor Johnson stated TDM program costs could create a large discrepancy between the
City and SunCal.
The Interim City Manager stated soft costs are not a made up delta; soft costs include
architecture, engineering, contingency and other costs that are not hardscape; capital
projects include all costs, not just hardscape.
Mayor Johnson stated the public would expect an extensive TDM program, which would be
very costly; a lot of resources would have to be dedicated to a TDM program to make it
work.
The Public Works Director stated the initiative lists bus rapid transit that would travel to
BART; staff came up with a per mile cost; identifying costs for cue jump lanes is difficult
without knowing the location of lanes.
The Interim City Manager stated nearly a dozen other cities were surveyed to check
calculations; the City used a methodology that made sense and was not made up.
Mayor Johnson inquired whether the 2% cap would limit existing parcel taxes or prevent
new parcel taxes.
Special Joint Meeting
Alameda City Council and 3
Board of Education
January 5, 2010
The Interim City Manager stated the 2% cap does not indicate what portion would fund the
infrastructure or operational shortfall; the 2% cap includes existing taxes for the hospital,
school and sewer that total under 0.2 %; whether a future parcel tax would go above the
2% depends on the development phase.
Board Member Jensen inquired whether a future tax passed could not be assessed if the
assessment reaches 2% at a later development phase.
Board Member Mooney inquired whether the cap would not apply to the School District
because the School District is not named in the initiative.
The Interim City Manager responded the initiative is silent on the issue; stated concluding
that the School District is excluded is not known; a tax approved by voters after the homes
are sold could go above the cap.
Board Member McMahon inquired whether the initiative would supercede the 2000 land
transfer Agreement between the City and School District; and whether charter schools are
included in the School District's enrollment to qualify for State matching funds; stated
charter schools are public facilities; adding together the numbers [of School District and
charter school students] may have increasing enrollment; inquired what impact school
opening times have on traffic models; questioned whether changing the school opening
time could help mitigate traffic; further questioned the impact of staggering school start
times on the City's gateways.
The Public Works Director stated staff could review whether the idea could be modeled.
Board Member McMahon stated his questions could all be answered at a later date.
The School District Chief Financial Officer stated only students in the District could be
claimed for State matching funds.
Board Member McMahon stated the District has 10,000 students, including 800 students
attending charter schools; inquired whether the State match applies to Alameda residents
attending charter schools, to which the School District Chief Financial Officer responded in
the affirmative.
The Public Works Director stated changing school start times would not change gateway
impacts because trips are internal.
Board Member McMahon and Councilmember Matarrese provided examples of traffic
increasing when school is in session and decreasing when on break.
Vice Mayor deHaan inquired whether the $65 million needed for schools is included in the
City's shortfall estimates, to which the Interim City Manager responded the $371 million
Special Joint Meeting
Alameda City Council and 4
Board of Education
January 5, 2010
does not include schools.
Vice Mayor deHaan stated the City has a 25% inclusionary housing requirement; the
initiative limits the amount to 15 %; inquired whether the difference is included in
calculations.
The Interim City Manager responded the amount is not included; stated that she does not
have an estimate for said amount.
Vice Mayor deHaan stated his estimate is at least $60 million [for additional require
inclusionary housing]; inquired whether escalation is included, to which the Interim City
Manager stated the amount is based on present value.
Vice Mayor deHaan stated that he would add $160 million more [for escalation].
Councilmember Matarrese stated the $500 million mentioned in the ballot argument is
based on three source documents; the first document is from the January 2009 Alameda
Reuse and Redevelopment Authority (ARRA) meeting; the Board was presented with a
figure of $185 million in tax increment; $185 million is in jeopardy due to State takings; in a
March 16, 2009 letter, the Navy assigned $108 million as the [land purchase] price; an
October 30, 2009 Off Agenda Report addressed staff estimates and the $200 million cap;
the estimates ran $100 to $175 million [above the cap]; adding up all the amounts totals
$462 million; the fee waivers are $52 million, which brings the amount to $1/2 billion; there
is a $1/2 billion hole; that he does not have reason to believe the source documents are
not true.
In response to School Board Member N. Tam's inquiry about conveyance, the Interim City
Manager stated the redevelopment agency is the middleman; the agency would buy the
land from the Navy and pass it onto the developer; documents between the City and the
Navy require that the City receive the land; the redevelopment agency would pay the
property seller [Navy] with money received from the property buyer [developer]; the Navy is
interested in receiving $108 million for the property.
The Redevelopment Manager stated there are no public pro formas; in March 2009, there
was a very general presentation to the ARRA; the only numbers included were illustrative
numbers of the fiscal analysis; actual numbers were not presented.
The Interim City Manager stated the City and developer would negotiate the purchase
price; the City is negotiating the pro forma with SunCal, which includes the land sale price;
the amount cannot be discussed because the City is in an Exclusive Negotiating
Agreement (ENA) [with SunCal].
Mayor Johnson requested SunCal representatives to explain how the school would be paid
for with the $200 million cap.
Special Joint Meeting
Alameda City Council and 5
Board of Education
January 5, 2010
Mr. Keliher stated the initiative is intended to be the framework for the Alameda Point
development concept; all of the details and nuisances would be negotiated in the DDA and
School Mitigation Agreements; school locations are very limited; the constraints are the
environmental conditions and State lands restrictions; other locations are not State lands
compatible; the current assumption is that [school mitigation] fees would be paid and that
the School District would be able to get matching funds; enrollment will be going up with
the development and the School District should be able to get State matching funds; the
business plan SunCal submitted did not show a lot of revenue or any revenue at all for the
school sites; SunCal does not believe there is a shortfall; SunCal is very committed to
having schools on site.
Mayor Johnson stated everyone is nervous about relying on receiving money from the
State to build the schools after all the State takings from cities and schools.
Mr. Keliher questioned whether the assumption is that there will be no redevelopment
funds; stated no one knows what the State will do.
Board Member Mooney inquired whether the Environmental Impact Report (EIR) or
California Environmental Quality Act (CEQA) documents include schools.
The Planning Services Manager responded in the affirmative; stated pursuant to case law,
payment of school mitigation fees is the mitigation if the jurisdiction has mitigation
requirements.
Board Member Mooney inquired whether the District has school mitigation fees, the
Planning Services Manager responded in the affirmative.
Board Member Mooney inquired how much are the fees, to which Mr. Keliher responded
about $25 million.
Board Member Mooney requested an explanation of the School Mitigation Agreement.
Amy Freilich, SunCal Senior Vice President, stated the Development Agreement (DA) only
relates to the City and does not relate to or bind the redevelopment agency or School
District; the redevelopment agency and School District are independent agencies under
State law and have full authority to enter into any agreement; the redevelopment agency
will not sell the land to SunCal unless the deal makes sense; the initiative is only part of
the deal; everything has been done assuming that SunCal would negotiate with the
redevelopment agency and the School District; SunCal is assuming it will enter into a
School Mitigation Agreement and wants to figure out how to build the school in advance of
when it would be required; the 2% cap goes away when the homeowner buys the land; the
cap does not bind future homeowners, retail owners or commercial owners; the cap is in
place for the term of the development; in order for SunCal to sell the development in the
Special Joint Meeting
Alameda City Council and 6
Board of Education
January 5, 2010
first round, the infrastructure development costs cannot exceed the 2 %, which is the
reasonable amount above which people will not expend dollars; the typical School
Mitigation Agreement would address: 1) land being dedicated and provided to the School
District; 2) infrastructure, which SunCal fully budgeted to provide to the School District; and
3) the $25 million [in mitigation fees] that SunCal has estimated, which is less than the
most recent school construction costs; SunCal's goal is to resolve the issues.
Board Member Jensen inquired whether the initiative provides any protection for the
School District.
Ms. Freilich responded the initiative, which is a zoning document not a school document,
does not address schools at all other than to say that a school will be built on site; stated
the initiative says a school will be built on the site as part of the public benefits.
Board Member Jensen inquired where said issue is included in the initiative.
Ms. Freilich responded that she was mistaken; stated the initiative includes that a library
will be built [as part of the public benefits], not a school.
Board Member Jensen inquired whether the initiative includes $25 million for a school.
Ms. Freilich responded the $25 million has nothing to do with the initiative; stated based on
the School District's current fee structure, the State would require payment of $25 million
[in mitigation fees] if all of the development at the site takes place; the State has said the
amount is the maximum that a developer can be required to pay as part of the CEQA
mitigation and that payment is considered full mitigation; SunCal has indicated that it is
willing to: 1) go over and above that [amount] with respect to contributions; 2) enter into a
School Mitigation Agreement; and 3) provide infrastructure; the pro forma put in the land
for free; SunCal is willing to talk about all of the issues with the School District, but has not
had the conversation yet because it [the project] is not far enough along.
Board Member Jensen stated the School District would like to do so as well and has tried
to do so over the past four or five months; inquired whether the $25 million for schools
would be part of the $200 million cap, to which Ms. Freilich responded in the negative.
Board Member Jensen stated the public benefits list in Table 8.1 [Exhibit E, page 8 -4]
includes a school facility project.
Ms. Freilich stated the cap on the public benefits is only in Exhibit F; a school is not listed
in the $200 million cap.
Board Member Jensen inquired whether the amount [$25 million] is an additional amount
[above the $200 million cap], to which Ms. Freilich responded in the affirmative; stated the
amount is additional as is the TDM program that is laid out in the document.
Special Joint Meeting
Alameda City Council and 7
Board of Education
January 5, 2010
Board Member Jensen stated the initiative states 14 out of the 21 projects would be funded
either partially or entirely by a public assessment that would be a tax, fee or charge
imposed only on property owners within the plan area; inquired whether the public
assessments would be part of the 2% cap.
Ms. Freilich responded these [projects on list] are all in the pro forma and are well under
the 2% cap even including the impact fees for the school.
Board Member Jensen stated the Department of Education requires: 1) that a proposed
school site cannot be within 2000 feet of a significant disposal of hazardous waste; and 2)
that the sites not be within an area of flood or dam flood inundation unless the cost of
mitigating the flood or inundation is reasonable; global warming might impact the site near
Encinal High School; inquired whether the site closer to the estuary would be subject to
flooding.
Mr. Keliher responded the project assumes sea level rise; stated the site adjacent to
Encinal High School is not in a flood plane; said site is one of the highest in the
development; as for the environmental conditions, SunCal would not be able to develop on
the land unless the land is cleaned, conveyed and approved by all regulators; the other
site is 1,000 feet from the estuary; the site is in a flood plane in the current state; the site
has to be mitigated, like other areas, if sea level rise is assumed; environmental problems
have not been identified for the area, except for above ground problems that SunCal has
to pay to mitigate.
Board Member Johnson inquired whether remediation costs are included in the $25
million, to which Mr. Keliher responded the [school] mitigation fee is not used for clean up.
The Planning Services Manager stated under State law, there is not an environmental
impact if the developer pays the school impact fee.
Board Member Mooney stated the State sets a maximum amount that school districts can
charge for school mitigation fees; requested to get an answer back regarding whether the
School District is at the maximum.
Mayor Johnson inquired whether the cost to [environmentally] mitigate the school site is
included in the $200 million cap, to which Mr. Keliher responded in the negative.
Board Member Jensen stated campaign literature says the developer will be required to
build a new school; inquired whether the statement is true.
Mr. Keliher responded SunCal knows new schools need to be built.
Board Member Spencer inquired whether the initiative process has been used in the City
Special Joint Meeting
Alameda City Council and 8
Board of Education
January 5, 2010
of Alameda before to create a DA, to which the Interim City Manager responded the City
Attorney indicated this type of initiative has not been used in the City before.
In response to Board Member Spencer's inquiry regarding fiscal neutrality, the Interim City
Manager stated the language does not say the developer will guarantee fiscal neutrality;
the normal process for cities that have had developer initiatives follows a different
sequence; the development project, DA and DDA are negotiated, then, the matter goes to
the ballot.
Board Member Spencer inquired whether Alameda has had any DAs that only include a
good faith effort [at fiscal neutrality], to which the City Attorney responded in the negative;
stated the provision would be inconsistent with the Council resolution that requires fiscal
neutrality to be guaranteed.
Board Member Spencer inquired whether the City has had any DAs that include a dollar
cap on public benefits, to which the Public Works Director responded the DAs he has seen
do not.
The City Attorney stated said provision is not normally in a DA; said type of provision
typically belongs in a DDA.
Board Member Spencer inquired whether Alameda has DAs that allow developers to sell
obligations and rights without the City's consent, to which the City Attorney responded the
City would not typically negotiate such a provision; stated that she does not know of any
DA with a provision that loose.
Board Member Spencer requested staff to explain why the City does not allow sale without
City consent.
The City Attorney stated the City needs to know the developer has the capacity to perform
entitlements; the City goes through a lengthy negotiation process with the developer it
chooses to get entitlements in place; cities want a say over the entity receiving
entitlements to ensure the entity has the financial capacity to perform.
Board Member Spencer inquired who benefits from the developer being able to sell without
the City's consent, to which the City Attorney responded the developer drafted the DA;
stated the DA is not a negotiated Agreement and would look to provide developer friendly
provisions; the provision is more developer friendly, than City friendly.
In response to Board Member Spencer's inquiry about citizens focusing on whether the
language protects the City, the Interim City Manager stated said question is a policy issue
to be decided by the City Council and School Board.
The Interim City Manager stated most DDAs include language restricting and controlling
Special Joint Meeting
Alameda City Council and 9
Board of Education
January 5, 2010
property transfer; the typical language usually says the developer can transfer with the
City's approval, which may not be reasonably withheld; some DDAs even preclude the
developer from selling for seven to ten years; SunCal is not a vertical developer; SunCal
develops master plans and sells them to be constructed by different companies.
Mayor Johnson stated the developer's Internal Rate of Return (IRR) was discussed when
the City went through the selection process; SunCal's requirement was 25 %; inquired
whether the IRR is still at 25 %.
The Interim City Manager stated the ENA prohibits the contents of the pro forma from
being addressed.
Mayor Johnson stated the confidential nature of the ENA prohibits the Council from asking
some questions it might want to ask; that she is wondering if SunCal has changed the IRR
projection.
Mr. Keliher responded the documents that went into the business plan are the guidelines
for the initiative; the IRR was 22% to 25 %, which is always the goal in any similar project;
Alameda Point has the advantage of being in a low risk market.
Councilmember Gilmore stated SunCal submitted the business plan in December; the City
and SunCal also jointly developed a pro forma that went to the Navy.
Mr. Keliher stated it [pro forma development] was done at the same time [as the business
plan submittal], which was December 19, 2008.
Councilmember Gilmore inquired whether the contents of the business plan helped inform
the election reports.
The Interim City Manager responded staff tried to analyze the initiative based on its
contents; looking at the document in isolation is difficult; the business plan was used as a
frame of reference just to gage and validate the analysis of the initiative; staff was very
careful not to include parts of the business plan that were not included in the initiative; the
business plan was not superimposed because the business plan is not being voted on; the
business plan was used to double check and ensure staff understood the initiative
contents.
The Redevelopment Manager stated staff focused on the initiative contents; the business
plan is still under negotiation; the ARRA has never taken action on the business plan;
there is no agreement on the business plan or joint pro forma; staff saw the two documents
[initiative and business plan] as being very separate and had to analyze only what is in the
initiative because the initiative will be legally binding if the voters approve it.
Councilmember Gilmore sated the contingency is included in the soft costs; inquired the
Special Joint Meeting
Alameda City Council and 10
Board of Education
January 5, 2010
percentage of the contingency.
The Public Works Director responded different contingencies were included based on the
level of analysis; stated contingencies are at 10 %, 20% and even 25 %; estimates were
based on details; Harris and Associates, the firm which worked on the Bayport project,
concurred that the estimates are reasonable and the contingency percentages are
reasonable and some could even be higher; that he polled other Public Works Directors to
confirm the estimates and contingencies are in line [with other projects].
Councilmember Gilmore inquired whether the density bonus would be available for any
project built at Alameda Point, to which the Planning Service Manager responded in the
affirmative; stated the State [density bonus] law trumps the cap in the initiative.
Councilmember Gilmore inquired whether Tax Increment (TI) financing has to be spent in
redevelopment areas; and whether Alameda Point is the City's largest redevelopment
area.
The Interim City Manager responded redevelopment agencies are formed to cure blight;
stated the initiative determines how TI dollars will be used, which is usually negotiated in
the DDA; there are other ways to use TI; the 80% stream could be leveraged for a tax
allocation bond; the proceeds of the tax allocation bonds could be used for a variety of
things within the project area; 20% of the TI can be used inside and outside of project
areas as long as it is spent on affordable housing.
Councilmember Gilmore stated the TDM is not spelled out in the initiative; inquired
whether there is anything preventing the City from requiring further TDM; stated that she is
not clear whether or not the TDM is part of the public benefits cap.
The Public Works Director responded staff has concluded that the TDM is included in the
public benefit cap based in the general definition of on site and off site traffic and transit
improvements; stated the concern is that staff does not know what is needed to really
mitigate traffic impacts; the TDM hits up against the $200 million cap and the 2% tax cap
for operation and maintenance; staff is concerned that the [$200 million] cap might be
exceeded when all public benefits are considered; the project also has to cover
maintenance in order to meet the Council resolution requiring fiscal neutrality.
Mr. Keliher stated SunCal's opinion is that it [TDM] is not included in the cap; the project
has to pay for it [TDM]; it [TDM] is part of the business plan and a number of different
things; TDM is outlined in Section 5.6 of the Specific Plan; there are not a lot of details
because that is what CEQA is for; a complete environmental review will be done; Council
approved starting the CEQA documents several months ago; SunCal gave $1/4 million
towards the effort.
Councilmember Gilmore stated various mitigations will be discussed at the end of the
Special Joint Meeting
Alameda City Council and 11
Board of Education
January 5, 2010
CEQA process; inquired whether said mitigations are part of the $200 million cap, to which
Mr. Keliher responded in the negative.
The Public Works Director stated the public benefit lists on site and off site traffic and
transit improvements; that he does not understand how TDM is not included in on site and
off site traffic and transit improvements.
The Interim City Manager stated Mr. Keliher's definition of what is referenced in the
Specific Plan is correct; the Public Works Director is also correct; there is an
inconsistency; there is language in the initiative that specifically says the TDM will be
assessed on the property; therefore, the TDM had to be included in the 2% cap.
Mr. Keliher stated there are going to be a lot of little gray areas and interpretations that
have to be addressed in the DDA: the contingency is 45 %: 25% for design level and
another additional 20% for the construction contingency aggregate to 45 %, which is pretty
high.
The Public Works Director stated the amounts depend on the level of detail; a reputable
civil engineering firm checked the amounts.
Councilmember Gilmore inquired whether the transfer of rights applies only to vertical
development.
Mr. Keliher responded SunCal has to create a pattern book or design guideline; stated the
community needs to know what SunCal says will be built is what will be built once the land
is sold off; the guidelines are overseen and approved by the Planning Board and City
Council; the other piece is conveyance documents with the Navy; there are other steps;
saying that there would not be City oversight is true to a certain extent; however, the City
approves everything that will go on the particular parcels that are going to be sold; there
are a lot of steps that SunCal has to go through to be able to sell the land; SunCal does
not want to have to go through a City process to see if a company wants to buy 20 lots;
they [the purchasing company] will have to go vertical in the way SunCal described it [the
project].
Board Member N. Tam inquired what is the City's plan to obtain funding to buy the land
from the Navy if the initiative fails.
The Interim City Manager responded the City and SunCal could come up with an
alternative between now and July 2010 if the initiative fails; if not, the Navy will accept
payment under a variety of scenarios; the City's negotiations with the Navy are to have
continued clean up of the property first; the City would proceed with some solution and
would not abdicate responsibility if the initiative fails and SunCal decides to check out;
several past scenarios have not worked out; the City keeps following through with plans to
develop the site; that she anticipates that the City will continue to do so.
Special Joint Meeting
Alameda City Council and 12
Board of Education
January 5, 2010
Mayor Johnson requested the Interim City Manager and School Superintendent to outline
the three largest risks; stated one risk for the School District would be if the initiative
passes and the District cannot reach an agreement with the developer.
The School Superintendent stated the guarantee of [building] schools and figuring out
generation rates are risks; one elementary school does not provide enough seats for 1,300
kids; going through the CEQA phasing is another big issue; currently, nothing is required
and legally binding in writing.
The Interim City Manager stated everything is about money; the three biggest issues are
money, money and money; there is a difference between what the initiative says and what
it intends; what is says is being voted on; based on her past experience, her first analysis
was that transit improvements alone would cost $1/4 billion; the numbers ended up being
$227 million; the initiative language pertaining to money is an issue.
Board Member Spencer moved approval of continuing the School Board meeting past
10:30 p.m.
Board Member N. Tam seconded the motion, which carried by unanimous voice vote — 5.
Mayor Johnson called a recess at 10:15 p.m. and reconvened the Special Joint meeting at
10:33 p.m.
Proponents (In Favor of Measure B): Joe Mallon, Alameda; Susan Decker, Alameda; Sam
Sause, Alameda; Christopher Seiwald, Alameda; Helen Sause, Alameda; Honora Murphy,
Alameda; Barbara Kahn, Alameda; David Walsh, Bladium Sports; Joan Konrad, Alameda;
Jon Spanger, Alameda; Doug Linney, Alameda; Michael Krueger, Alameda; and Doug
Biggs, Alameda.
Opponents: (Not in Favor of Measure B): Dave Needle, Alameda; Rosemary McNally,
Alameda; Irene Dieter; Ashley Jones, Alameda; Janet Davis, Alameda; Mary Fetherolf,
Alameda; David Howard, Alameda; Gail deHaan, Alameda; Tony White, Alameda; Richard
Bangert, Alameda; Jim Sweeney, Alameda; Former School Board Member Janet Gibson,
Alameda; Jay Ingram; Carole Brandmeyer, Alameda; Corinne Lambden, Alameda; and
Gretchen Lipow, Alameda.
ADJOURNMENT
There being no further business, Mayor Johnson adjourned the Joint Meeting at 11:38 p.m.
Respectfully submitted,
Special Joint Meeting
Alameda City Council and 13
Board of Education
January 5, 2010
Lara Weisiger
City Clerk
The agenda for this meeting was posted in accordance with the Brown Act.