2006-11-01 ARRA PacketAGENDA
Regular Meeting of the Governing Body of the
Alameda Reuse and Redevelopment Authority
Alameda City Hall
Council Chamber, Room 390
2263 Santa Clara Avenue
Alameda, CA 94501
1. ROLL CALL
2. CONSENT CALENDAR
Wednesday, November 1, 2006
Meeting will begin at 7:00 p.m.
Consent Calendar items are considered routine and will be enacted, approved or adopted by one motion unless a
request for removal for discussion or explanation is received from the Board or a member of the public.
2 -A. Approval of the minutes of the Regular Meeting of October 4, 2006.
2 -B. Recommendation to approve consultant agreement with Moffatt & Nichol Engineers for
Pier Condition Analysis at Alameda Point in an amount not to exceed $170,226
3. REGULAR AGENDA ITEMS
3 -A. Alameda Point Project Update
3 -B. Alameda Point Environmental Remediation Update: Western Shoreline — IR Sites 1,2, and
32, Soil at IR Site 25 (Coast Guard North Housing), and Compliance with Marsh Crust
Ordinance
4. ORAL REPORTS
4 -A. Oral report from Member Matarrese, Restoration Advisory Board (RAB) representative.
5. ORAL COMMUNICATIONS, NON - AGENDA (PUBLIC COMMENT)
(Any person may address the governing body in regard to any matter over which the
governing body has jurisdiction that is not on the agenda.)
6. COMMUNICATIONS FROM THE GOVERNING BODY
7. ADJOURNMENT
This meeting will be cablecast live on channel 15.
Notes:
• Sign language interpreters will be available on request. Please contact the ARRA Secretary at 749 -5800 at
least 72 hours before the meeting to request an interpreter.
• Accessible seating for persons with disabilities (including those using wheelchairs) is available.
• Minutes of the meeting are available in enlarged print.
• Audio tapes of the meeting are available for review at the ARRA offices upon request.
APPROVED
MINUTES OF THE REGULAR MEETING OF THE
ALAMEDA REUSE AND REDEVELOPMENT AUTHORITY
Wednesday. October 4, 2006
The meeting convened at 7:05 p.m. with Chair Johnson presiding.
1. ROLL CALL
Present: Beverly Johnson, Chair of Alameda
Doug deHaan, Boardmember, City of Alameda
Frank Matarrese, Boardmember, City of Alameda
Tony Daysog, Boardmember, City of Alameda
Absent: Marie Gilmore, Boardmember, City of Alameda
2. CONSENT CALENDAR
2 -A. Approval of the minutes of the Regular Meeting of September 6, 2006.
Approval of 2 -A was motioned by Member deHaan, seconded by Member Matarrese and
passed by the following voice vote: Ayes — 4; Noes — 0; Abstentions —1.
2 -B. Approval of Subleases at Alameda Point.
Member deHaan had questions about two of the subleases due to their duration and requested
information about the specific tenants, as well as an overview of current leasing prospects.
Nanette Banks, Finance and Administration of DSD, explained that TransFreight Express wants
to relocate their corporate headquarters and distribution center at Alameda Point. The other lease
is to Makani for Building 19 to be used as R &D and office space. It is an alternative energy
(wind- based) company that may also be interested in using the runways for experiments. Leslie
Little, Development Services Manager, indicated that there continues to be ongoing interest in
the buildings at Alameda Point, but pointed out the obviously expensive building improvements
necessary to make them usable, which tends to limit some potential businesses.
Approval of 2 -B was motioned by Member deHaan, seconded by Member Matarrese and
passed by the following voice vote: Ayes — 4; Noes — 0; Abstentions —1.
2 -C. Recommendation to authorize the Executive Director to Execute a contact agreement with
WRT /Solomon E.T.C. in the amount of $250,000 to complete Station Area planning activities
for Alameda Point.
Member deHaan inquired about the source of the $250,000 and whether we are in a position
today to approve the contract, given the master developer situation. Debbie Potter, Base Reuse
and Community Development Manager, explained that this is pursuant to a $250,000 grant
received from MTC — with City contribution of $3,000 — for the purpose of more detailed
planning of the transit node. To not go forward at this time means losing the grant. This study
will impact future land development plans; traffic and transit issues will need to be addressed
regardless of who the developer is.
Page 2
There was one speaker on this item, Diane Lichtenstein, who praised the four workshops
outlined in the contract and requested that after each workshop a summary report to be generated
(perhaps in the local newspaper as well as the City's website). She also recommended
expanding the scope of the ferry analysis beyond the half -mile radius of the station as presently
indicated. She also requested that all drafts of the report be available electronically.
Approval of 2 -C was motioned by Member Matarrese, seconded by Member deHaan and
passed by the following voice vote: Ayes — 4; Noes — 0; Abstentions —1.
3. REGULAR AGENDA ITEMS
3 -A. Status Report on East Bay Regional Park District Request for Long -Term Lease.
Debbie Potter, Base Reuse and Community Development Manager, stated that, at the September
ARRA meeting, East Bay Regional Park District (EBRPD) representatives Doug Siden and Mike
Anderson indicated that EBRPD is ready to begin funding improvements at the 26 -acre
Enterprise Park through the use of Measure AA and Proposition 12 money (totaling $500,000).
A portion of the Proposition 12 funds ($100,000) specify that land must be secured by the end of
this year, and the project must be completed and the money expended by the end of next year. It
also requires a 20 -year lease on the land. According to the staff report, there could be a smaller,
Phase 1 lease or a lease for the entire 26 acres. There are several other leases in place that
encumber some portions of the 26 acres, including Alameda Soccer Club (until 2008) and the
Hobby Shop (until 2010).
Member Daysog mentioned that 11 years ago, there was concern that EBRPD wanted an RV
parking lot as part of their plan for this land. Ms. Potter confirmed that this is no longer an
option.
Doug Siden, elected EBRPD representative, reiterated the funding and timing requirements. He
introduced Mike Anderson, Assistant General Manager, who presented a map of the proposed
area and plans. It consists of 10.6 acres and excludes current leased properties. Ultimately, the
District would like the entire 26 acres but could start with this plan. Proposed plans include
family picnic sites, clean up of the tennis and basketball courts, development of the shoreline
trail to tie to the existing beach area, and clean up of the beach and boat launch areas. Future
plans include a natural planning resource area and interpretive center, as well as boating
instruction at the marina.
Chair Johnson pointed out that other community groups have looked at this site, and also
questioned what would happen if the community would rather keep some of the facilities as they
are. Mr. Anderson responded that if the City prefers to have more community input about use of
this area, EBRPD could either use $100,000 of the funds somewhere else in order to not lose
them — trimming their ultimate project to $400,000 — or use that first $100,000 to simply clean
up the beach area and shoreline trail. Chair Johnson stressed that more community feedback
about what type of use for the area is preferable is needed before committing to a 20 -year lease.
Member Matarrese felt that the primary areas to spend the $500,000 should be the beach, bay
trail and picnic grounds. Mr. Anderson agreed that this should be doable and hoped to move
Page 3
forward in negotiating a lease for these specific areas. Member deHaan expressed his desire that
EBRPD continue to be involved in the area and asked how the funding stream would be
maintained in the future. Mr. Anderson indicated that possibly a small assessment district would
have to be established if the project becomes larger. Member Matarrese stated that he would like
a long -term commitment from EBRPD for the area. The consensus among ARRA members and
EBRPD was the first priority is extending the Bay Trail from the boat ramp along the beach to
the Hornet; if additional funds remain, the other areas will be considered.
Member Matarrese motioned that EBRPD make improvements on the Bay Trail from the
existing boat ramp as far north as possible, including cleaning up the beach. If additional
funds remain, they would be used for the picnic area and former RV parking lot. Staff was
directed to negotiate a lease with EBRPD to accomplish this. Member Daysog seconded the
motion, and the motion passed unanimously.
3 -B. Alameda Point Project Update.
Debbie Potter, Acting Alameda Point Project Manager, gave an Alameda Point update
presentation to the Board. The presentation included a chronology of the ARRA's negotiations
with the Navy and an explanation to the community on how we went from "no cost" to .paying
$108.5 million for the Navy property. Ms. Potter also discussed the master developer, APCP's,
election not to proceed with the project and presented staffs recommendation for an initial next
step.
Ms Potter summarized the genesis of how we got from a no cost EDC to a 108.5 million dollar
purchase price: She explained how the ARRA's PDC and the general plan call for over 3 million
square feet of commercial development. In January 2004, however, the Navy sent a letter
requesting that we submit a formal amendment to our "no- cost" EDC application to formerly
make the case about why we felt like we continued to be eligible for a "no- cost" EDC. The
Navy's letter further stated that it could not continue to work with us to negotiate on our early
transfer without such an amendment. The letter also said that they were more than happy to
negotiate a "for- cost" EDC with the ARRA. Because the Navy would be the ultimate entity to
deciding whether or not we were still eligible for the no cost EDC and because they had clearly
communicated to us that they felt we were no longer eligible and because legislation was in the
works to preclude no cost EDC's in the future, the ARRA made a decision that it would be more
effective if we sat down and negotiated with the Navy for a "for - cost "conveyance. We started
our "New Beginnings" with the Navy in 2004 but the federal government also eliminated no cost
economic development in 2004 and none of the bases that are closed as part of the BRAC 5 are
going to eligible for a no cost economic development conveyance, most of those properties are
going to be disposed of as is where is. So it took us a little over 2 years to negotiate with the
Navy to prepare the PDC and to negotiate a land price. And in June of this year we concluded
negotiations with the Navy with a draft term sheet that included a $108.5 million dollar purchase
price. On September 21st, APCP withdrew from the project, citing the downturn in the
residential market and that they could no longer support the $108.5 million line price given the
land plan.
Page 4
With that negotiation process and chronology behind us, and the withdrawal of our Master
Developer, Staff is proposing, as the initial next step, that we test the market through a request
for qualifications (RFQ) process with the current term sheet. b1 the event that we are unable to
identify a replacement development then we would work with the Navy on an alternate
disposable strategy, most likely a public sale, an approach that the Navy had been taking of late.
Chair Johnson asked about the on -going work with the Navy, in the event that a buyer under the
current term sheet doesn't come forward. Ms. Potter answered that we will continue to run our
leasing program, and the Navy will continue to run it's environmental clean up program. Chair
Johnson also asked about the cost of working with the Navy to move forward with alternatives if
a replacement developer isn't identified. Ms. Potter explained that the ARRA's budget did
consider a scenario where the master developer didn't go forward and staff is funded in the
ARRA budget and consultants would probably need far fewer consultants then we've had when
we've been in activity negotiations on a term sheet and those kind of things, but we would still
need to work with our environmental consultant and our out side counsel, those costs are
included in the ARRA's budget.
To answer Chair Johnson's question about what types of consultants would we still continue to
need, Ms. Potter answered that we would continue to use an environmental consultant because
we comment on all of the Navy environmental clean up documents. Chair Johnson asked if we
should ask the Navy to pay for the consultants at that point.
David Brandt, Deputy Executive Director, clarified that these are consultants that we use to
protect the City's interest when it comes to the work that the Navy's doing on clean up as well as
if there gonna be issuing opinions about the tidelands trust, then we need to have our experts
weighing in about the tidelands trust and where were believe the legal issues are and those kinds
of things.
Member Daysog began a discussion regarding the ARRA's no -cost EDC agreement with the
United States Navy. He referenced several paragraphs of the Navy's letter to Debbie Potter dated
April 7, 2003 regarding the basis for the Navy approval of a no cost EDC. Member Daysog is
very concerned about the $108 million purchase price, stating that if APCP couldn't work it
through, that it would be difficult to find a replacement master developer. He'd rather see the
$108 million go toward public amenities that have been contemplated.
The Chair, Boardmembers and Staff discussed, at length, the challenges we faced and the
available options we continue to deal with in order to move forward. Member deHaan and Chair
Johnson discussed researching a concept that looks at phases in the future to anticipate changes
in the market. The Board also expressed their interest in going back to a no -cost EDC (build less
residential), but Ms. Potter explained that, according to the Navy, a no -cost EDC was dead,
because a project that included less residential was not economically viable. She said, however,
that if the ARRA desires, we could continue discussions with the Navy about convincing them
that were still eligible for our no cost EDC. She further discussed that the ARRA does have an
agreement, an executed MOA with the Navy, but that the Navy is going to require us to submit
an amendment to that no cost EDC.
Page 5
David Brandt further clarified the more fundamental legal problem which is, we would have to
amend our EDC application and unfortunately, the Navy will argue that there's no more legal
authority over a no cost EDC so we would be essentially be giving up our no cost EDC.
Chair Johnson and Member Matarrese would like more information and analysis about whether
we are legally able to hold the Navy to the existing no -cost EDC agreement.
Member Daysog expressed the importance of involving the public so that the $108 million isn't
spent on projects that veer so far away from the community resource reuse plan and the public
amenities that have already been contemplated. Ms. Potter addressed Member Daysog's concern
by noting that the negotiated price of $108.5 million was based on a proforma that provided
fiscal neutrality, provided for the sports complex, provided for the open space, provided for 25%
affordable housing, so all of the goals that has been identified over the years were taken into
account and provided for with that land purchase price. Granted that tax increment was pledged
to the project that was part of it too, but it provided in all of the transit, the shuttle, the ecopath is
all of the things that have been talked about over the last several years, were all accounted for in
the proforma that had the $108.5 million dollar land purchase price.
Member deHaan asked about the process used at other closed military bases, including Mare
Island and the Presidio. David Brandt explained that the Presidio was conveyed under a trust but
that federal legislation is needed for that. Mr. Brandt said that we could approach our delegation
to ask if that's feasible.
The first speaker on this item, Pam Telschow, expressed how glad she was that the ARRA was
going back to consider every option and that they are not just going to jump into looking for a
new Master Developer. Chair Johnson expressed her opinion that she felt it was a remote
possibility that another developer would just step right in where APCP left off. The second
speaker, Helen Sause, also echoed Ms. Telschow's concerns and the direction of the Board,
urging them to select and find those developers that have very deep experiences in commercial,
light industrial retail, and other forms of development. She also suggested that the selection
process involve the community. Chair Johnson wanted the public to have a full understanding
that although the Development Services Dept. has received numerous inquiries, those inquiries
may not be viable. The third speaker, Elizabeth Krase, recommended we find a master developer
that would keep keeps more of the historic buildings.
Member Matarrese commented that he is heartened by the attendance of tonight's meeting and
that it's very important that we also look at the strength of our controls on the planning and our
city restrictions on development. He further stated that the comments from the speakers are
valuable and would like to see them translated into where we go forward. Member Daysog
commented that it's absolutely vital for the City of Alameda through the ARRA to continue to be
a leader in converting the base and to not allow the Navy to be in the drivers seat through a
public action process. There was further discussion about the caretaking of the property and
requesting that the Navy return to those responsibilities.
Debbie Potter summarized the direction from the Board and other issues to explore: researching
the legality and shear logistics of the numbers to see if we can revert back to a no -cost EDC; the
Page 6
parallel path of moving forward with an RFQ process to see if there is a developer who wants to
step into the existing field; a public sale; federal legislation on a trust; caretaker issues, etc.
A motion to initiate an RFQ and to reevaluate all other options discussed was motioned by
Chair Johnson and seconded by Member deHaan and passed by the following voice vote:
Ayes — 4; Noes — 0; Abstentions — 0.
4. ORAL REPORTS
4 -A. Oral report from Member Matarrese, RAB representative.
Member Matarrese attended the September 7th meeting, highlighting issues regarding additional
radiological testing of sites 1,2, and 32. There was also an update on site 25, the Coast Guard
north housing and a observation of a violation of the marsh crust ordinance (trenching and
digging). Member Matarrese would like the City to investigate further.
ORAL COMMUNICATIONS, NON - AGENDA (PUBLIC COMMENT)
None.
6. COMMUNICATIONS FROM THE GOVERNING BODY
Per Member Matarrese's earlier discussion of the RAB meeting regarding Site 25, Member
deHaan requested an update at the next regular ARRA meeting on the status of Site 25.
7. ADJOURNMENT
Meeting was adjourned at 9:20 p.m.
Respectfully submitted,
Irma Glidden
ARRA Secretary
Alameda Reuse and Redevelopment Authority
Interoffice Memorandum
November 1, 2006
TO:
FROM:
SUBJ:
Background
Honorable Chair and Members of the
Alameda Reuse and Redevelopment Authority
Debra Kurita, Executive Director
Recommendation to Approve Consultant Agreement with Moffatt & Nichol Engineers for
Pier Condition Analysis at Alameda Point in an amount not to exceed $170,226
At the April 2006 ARRA meeting, the ARRA approved the 20 -year sublease with the Maritime
Administration (MARAD). As part of that lease, the ARRA requested that a condition assessment be done
on the piers to ensure compliance with the lease requirements.
Discussion
The condition assessment plan for the piers at Alameda Point will require structural, civil, electrical and
mechanical engineers as well as divers. Inspection of the above water and below water facilities will occur
as well as structural assessments of the decks, moorings, and utilities. The final report will summarize the
results of the assessments and note deficiencies in the facility.
Three bids were received for the project from CH2M Hill ($410,000), Moffatt & Nichol ($170,226) and
Power Engineering ($300,500). Moffatt & Nichol (M &N) has provided engineering services to Alameda
Point on many occasions. In 1996, they were selected by competitive bid to provide a preliminary
condition report on the piers for the Community Reuse Plan. In 1998, they were selected to prepare a
Detailed Utility Study funded by the Office of Economic Adjustment. In 2004, M &N was selected to
prepare a mooring plan for the USS Hornet at Pier 1.
In addition to the request for a pier condition assessment, MARAD has requested that the ARRA examine
the depth of the water adjacent to the piers. M &N will also perform that work as part of this contract.
Fiscal Impact
The proposed contract totals $170,226. The approved MARAD budget included an estimate of $150,000
for the pier condition study and anticipated $420,000 port services cost. In August, the ARRA approved
$325,000 port contract, resulting in $95,000 savings. The additional $20,226 for the pier assessment will
come from the cost savings.
Recommendation
It is recommended that the Alameda Reuse and Redevelopment Authority approve the consultant
agreement with Moffatt & Nichol Engineers for Pier Condition Analysis at Alameda Point.
Agenda Item 2 -B CC
11 -1 -06 ARRA
Honorable Chair and Members of the November 1, 2006
Alameda Reuse and Redevelopment Authority Page 2
Re.pe ,fully +ted,
Leslie Little
Development Services Director
By: Nanette Banks
Finance & Administration Manager
DK/LAL/NB:dc
Attachments: Bid Analysis
Proposed Contract with Moffatt & Nichol
Project:
laRealty Group
REAL ESTATE SERVICES
Bid Analysis
Alameda Point
Pier 1, 2 & 3 - Inspection
MARAD Lease
Based on: Moffatt & Nichols - Scope of Work
Scrwe of Work:
1 )current search
2. Above water inspection
3. Underwater inspection
4. Above deck structural assessment
5. Mooring Hardware Assessment
6. Facility Assessment - Civil
7. Facility Assessment - Electrical
8. Facility Assessment - Mechanical
9. Report
10. Attend Meetings
Date: October 20, 2006
Prepared by: Mele Payne Lynch
Director - Construction
Distribution: Nanette Banks (w/ attach for approval)
Manny Moreno (w /attach)
Bids Received: Not exceed price
Moffatt & Nichols $170,226
Power Engineering $300,500
CH2M Hill $410,000
Attachment 1
Agenda Item #2 -B CC
11 -1 -06 ARRA
CONSULTANT AGREEMENT
THIS AGREEMENT, entered into this 1st day of November 2006, by and between the
ALAMEDA REUSE AND REDEVELOPMENT AUTHORITY, a Joint Powers Authority,
(hereinafter referred to as "ARRA "), and Moffatt & Nichol Engineers, a California corporation,
whose address is 2001 North Main Street, Suite 360, Walnut Creek, CA 94596 (hereinafter
referred to as "Consultant "), is made with reference to the following:
RECITALS:
A. ARRA is a Joint Powers Authority established by the City of Alameda and the
Community Improvement Commission under the California Joint Exercise of Powers Act and a
public entity lawfully created and existing under the State of California with the power to carry
on its business as it is now being conducted.
B. Consultant is specially trained, experienced and competent to perform the special
services which will be required by this Agreement; and
C. Consultant possesses the skill, experience, ability, background, certification and
knowledge to provide the services described in this Agreement on the terms and conditions
described herein.
D. ARRA and Consultant desire to enter into an agreement to provide engineering
services for FY2006 -2007 Condition Assessment of Piers 1, 2 and 3 for MARAD occupancy,
upon the terns and conditions herein.
NOW, THEREFORE, it is mutually agreed by and between the undersigned parties as
follows:
1. TERM:
The tern of this Agreement shall commence on the 1st day of November 2006, and shall
terminate on the 30th day of June 2007, unless terminated earlier as set forth herein.
2. SERVICES TO BE PERFORMED:
Consultant shall perform each and every service set forth in Exhibit "A" which is
attached hereto and incorporated herein by this reference.
3. COMPENSATION TO CONSULTANT:
Consultant shall be compensated for services performed pursuant to this Agreement in
the amount not to exceed $170,226.00 as set forth in Exhibit "A" which is attached hereto and
incorporated herein by this reference.
4. TIME IS OF THE ESSENCE:
Consultant and ARRA agree that time is of the essence regarding the performance of this
Agreement.
Moffatt & Nichol Engineers
October 2006
Attachment 2
Agenda Item #2 -B CC
11 -1 -06 ARRA
Page 1
5. STANDARD OF CARE:
Consultant agrees to perform all services hereunder in a manner commensurate with the
prevailing standards of like professionals in the San Francisco Bay Area and agrees that all
services shall be performed by qualified and experienced personnel who are not employed by the
ARRA nor have any contractual relationship with ARRA.
6. INDEPENDENT PARTIES:
ARRA and Consultant intend that the relationship between them created by this
Agreement is that of employer- independent contractor. The manner and means of conducting the
work are under the control of Consultant, except to the extent they are limited by statute, rule or
regulation and the express terms of this Agreement. No civil service status or other right of
employment will be acquired by virtue of Consultant's services. None of the benefits provided by
ARRA to its employees, including but not limited to, unemployment insurance, workers'
compensation plans, vacation and sick leave are available from ARRA to Consultant, its
employees or agents. Deductions shall not be made for any state or federal taxes, FICA
payments, PERS payments, or other purposes normally associated with an employer- employee
relationship from any fees due Consultant. Payments of the above items, if required, are the
responsibility of Consultant.
7. IMMIGRATION REFORM AND CONTROL ACT (IRCA):
Consultant assumes any and all responsibility for verifying the identity and employment
authorization of all of his /her employees performing work hereunder, pursuant to all applicable
IRCA or other federal, or state rules and regulations. Consultant shall indemnify and hold ARRA
harmless from and against any loss, damage, liability, costs or expenses arising from any
noncompliance of this provision by Consultant.
8. NON - DISCRIMINATION:
Consistent with ARRA's policy that harassment and discrimination are unacceptable
employer /employee conduct, Consultant agrees that harassment or discrimination directed
toward a job applicant, a ARRA employee, or a citizen by Consultant or Consultant's employee
or subcontractor on the basis of race, religious creed, color, national origin, ancestry, handicap,
disability, marital status, pregnancy, sex, age, or sexual orientation will not be tolerated.
Consultant agrees that any and all violations of this provision shall constitute a material breach
of this Agreement.
9. HOLD HARMLESS:
Consultant shall indemnify, defend, and hold harmless ARRA, its Board, officials,
employees, and volunteers ( "Indemnitees ") from and against any and all loss, damages, liability,
claims, suits, costs and expenses whatsoever, including reasonable attorneys' fees ( "Claims "),
arising from or in any manner connected to Consultant's negligent act or omission, whether
alleged or actual, regarding performance of services or work conducted or performed pursuant to
this Agreement. If Claims are filed against Indemnitees which allege negligence on behalf of the
Consultant, Consultant shall have no right of reimbursement against Indemnitees for the costs of
defense even if negligence is not found on the part of Consultant. However, Consultant shall not
be obligated to indemnify Indemnitees from Claims arising from the sole or active negligence or
willful misconduct of Indemnitees.
Moffatt d'• Nichol Engineers
October 2006 Page 2
As to Claims for professional liability only, Consultant's obligation to defend
Indemnitees (as set forth above) is limited to the extent to which its professional liability
insurance policy will provide such defense costs.
10. INSURANCE:
On or before the commencement of the term of this Agreement, Consultant shall furnish
ARRA with certificates showing the type, amount, class of operations covered, effective dates
and dates of expiration of insurance coverage in compliance with paragraphs 10A, B, C, D and
E. Such certificates, which do not limit Consultant's indemnification, shall also contain
substantially the following statement: "Should any of the above insurance covered by this
certificate be canceled or coverage reduced before the expiration date thereof, the insurer
affording coverage shall provide thirty (30) days' advance written notice to the ARRA by
certified mail, Attention: Risk Manager." It is agreed that Consultant shall maintain in force at
all times during the performance of this Agreement all appropriate coverage of insurance
required by this Agreement with an insurance company that is acceptable to ARRA and licensed
to do insurance business in the State of California. Endorsements naming the ARRA as
additional insured shall be submitted with the insurance certificates.
A. COVERAGE:
Consultant shall maintain the following insurance coverage:
(1) Workers' Compensation:
Statutory coverage as required by the State of California.
(2) Liability:
Commercial general liability coverage in the following minimum limits:
Bodily Injury: $500,000 each occurrence
$1,000,000 aggregate - all other
Property Damage: $100,000 each occurrence
$250,000 aggregate
If submitted, combined single limit policy with aggregate limits in the
amounts of $1,000,000 will be considered equivalent to the required
minimum limits shown above.
(3) Automotive:
Comprehensive automotive liability coverage in the following minimum
limits:
Bodily Injury: $500,000 each occurrence
Property Damage: $100,000 each occurrence
or
Combined Single Limit: $500,000 each occurrence
(4) Professional Liability:
Professional liability insurance which includes coverage for the
professional acts, errors and omissions of Consultant in the amount of at
least $1,000,000.
B. SUBROGATION WAIVER:
Consultant agrees that in the event of loss due to any of the perils for which he /she has
agreed to provide comprehensive general and automotive liability insurance, Consultant shall
look solely to his /her insurance for recovery. Consultant hereby grants to ARRA, on behalf of
Moffatt & Nichol Engineers
October. 2006 Page 3
any insurer providing comprehensive general and automotive liability insurance to either
Consultant or ARRA with respect to the services of Consultant herein, a waiver of any right to
subrogation which any such insurer of said Consultant may acquire against ARRA by virtue of
the payment of any loss under such insurance.
C. FAILURE TO SECURE:
If Consultant at any time during the term hereof should fail to secure or maintain the
foregoing insurance, ARRA shall be permitted to obtain such insurance in the Consultant's name
or as an agent of the Consultant and shall be compensated by the Consultant for the costs of the
insurance premiums at the maximum rate permitted by law and computed from the date written
notice is received that the premiums have not been paid.
D. ADDITIONAL INSURED:
ARRA, its Board, officers, employees and volunteers shall be named as an additional
insured under all insurance coverages, except any professional liability insurance, required by
this Agreement. The naming of an additional insured shall not affect any recovery to which such
additional insured would be entitled under this policy if not named as such additional insured.
An additional insured named herein shall not be held liable for any premium, deductible portion
of any loss, or expense of any nature on this policy or any extension thereof. Any other insurance
held by an additional insured shall not be required to contribute anything toward any loss or
expense covered by the insurance provided by this policy.
E. SUFFICIENCY OF INSURANCE:
The insurance limits required by ARRA are not represented as being sufficient to protect
Consultant. Consultant is advised to confer with Consultant's insurance broker to determine
adequate coverage for Consultant.
11. CONFLICT OF INTEREST:
Consultant warrants that it is not a conflict of interest for Consultant to perform the
services required by this Agreement. Consultant may be required to fill out a conflict of interest
form if the services provided under this Agreement require Consultant to make certain
governmental decisions or serve in a staff capacity as defined in Title 2, Division 6, Section
18700 of the California Code of Regulations.
12. PROHIBITION AGAINST TRANSFERS:
Consultant shall not assign, sublease, hypothecate, or transfer this Agreement, or any
interest therein, directly or indirectly, by operation of law or otherwise, without prior written
consent of ARRA. Any attempt to do so without said consent shall be null and void, and any
assignee, sublessee, hypothecate or transferee shall acquire no right or interest by reason of such
attempted assignment, hypothecation or transfer. However, claims for money by Consultant from
ARRA under this Agreement may be assigned to a bank, trust company or other financial
institution without prior written consent. Written notice of such assignment shall be promptly
furnished to ARRA by Consultant.
The sale, assignment, transfer or other disposition of any of the issued and outstanding
capital stock of Consultant, or of the interest of any general partner or joint venturer or syndicate
member or cotenant, if Consultant is a partnership or joint venture or syndicate or cotenancy,
which shall result in changing the control of Consultant, shall be construed as an assignment of
this Agreement. Control means fifty percent (50 %) or more of the voting power of the
corporation.
Moffatt d'• Nichol Engineers
October 2006 Page 4
13 . SUBCONTRACTOR APPROVAL:
Unless prior written consent from ARRA is obtained, only those people and
subcontractors whose names and resumes are attached to this Agreement shall be used in the
performance of this Agreement.
In the event that Consultant employs subcontractors, such subcontractors shall be
required to furnish proof of workers' compensation insurance and shall also be required to carry
general, automobile and professional liability insurance in reasonable conformity to the
insurance carried by Consultant. In addition, any work or services subcontracted hereunder shall
be subject to each provision of this Agreement.
14. PERMITS AND LICENSES:
Consultant, at his /her sole expense, shall obtain and maintain during the term of this
Agreement, all appropriate permits, certificates and licenses including, but not limited to, a
ARRA Business License, that may be required in connection with the performance of services
hereunder.
15. REPORTS:
A. Each and every report, draft, work product, map, record and other document,
hereinafter collectively referred to as "Report", reproduced, prepared or caused to be prepared by
Consultant pursuant to or in connection with this Agreement, shall be the exclusive property of
ARRA. Consultant shall not copyright any Report required by this Agreement and shall execute
appropriate documents to assign to ARRA the copyright to Reports created pursuant to this
Agreement. Any Report, information and data acquired or required by this Agreement shall
become the property of ARRA, and all publication rights are reserved to ARRA.
B. All Reports prepared by Consultant may be used by ARRA in execution or
implementation of:
(1) The original Project for which Consultant was hired;
(2) Completion of the original Project by others;
(3) Subsequent additions to the original project; and /or
(4) Other ARRA projects as appropriate.
C. Consultant shall, at such time and in such form as ARRA may require, furnish
reports concerning the status of services required under this Agreement.
D. All Reports required to be provided by this Agreement shall be printed on
recycled paper. All Reports shall be copied on both sides of the paper except for one original,
which shall be single sided.
E. No Report, information or other data given to or prepared or assembled by
Consultant pursuant to this Agreement shall be made available to any individual or organization
by Consultant without prior approval by ARRA.
1 6. RECORDS:
Consultant shall maintain complete and accurate records with respect to sales, costs,
expenses, receipts and other such information required by ARRA that relate to the performance
of services under this Agreement.
Consultant shall maintain adequate records of services provided in sufficient detail to
permit an evaluation of services. All such records shall be maintained in accordance with
generally accepted accounting principles and shall be clearly identified and readily accessible.
Moffatt cC Nichol Engineers
Ocioher 2006 Page 5
Consultant shall provide free access to such books and records to the representatives of ARRA or
its designees at all proper times, and gives ARRA the right to examine and audit same, and to
make transcripts therefrom as necessary, and to allow inspection of all work, data, documents,
proceedings and activities related to this Agreement. Such records, together with supporting
documents, shall be kept separate from other documents and records and shall be maintained for
a period of three (3) years after receipt of final payment.
If supplemental examination or audit of the records is necessary due to concerns raised by
ARRA's preliminary examination or audit of records, and the ARRA's supplemental examination
or audit of the records discloses a failure to adhere to appropriate internal financial controls, or
other breach of contract or failure to act in good faith, then Consultant shall reimburse ARRA for
all reasonable costs and expenses associated with the supplemental examination or audit.
17. NOTICES:
All notices, demands, requests or approvals to be given under this Agreement shall be
given in writing and conclusively shall be deemed served when delivered personally or on the
second business day after the deposit thereof in the United States Mail, postage prepaid,
registered or certified, addressed as hereinafter provided.
All notices, demands, requests, or approvals from Consultant to ARRA shall be
addressed to ARRA at:
Development Services Department
950 W. Mali Square, 2" `1 Floor
Alameda CA 94501
Attention: Nanette Banks
All notices, demands, requests, or approvals from ARRA. to Consultant shall he
addressed to Consultant at:
Moffatt & Nichol Engineers
2001 North Main Street, Suite 360
Walnut Creek, CA 94596
Attention: Richard M. Rhoads, P.E.
18. TERMINATION:
In the event Consultant fails or refuses to perform any of the provisions hereof at the time
and in the manner required hereunder, Consultant shall be deemed in default in the performance
of this Agreement. If such default is not cured within a period of two (2) days after receipt by
Consultant from ARRA of written notice of default, specifying the nature of such default and the
steps necessary to cure such default, ARRA may terminate the Agreement forthwith by giving to
the Consultant written notice thereof.
ARRA shall have the option, at its sole discretion and without cause, of terminating this
Agreement by giving seven (7) days' prior written notice to Consultant as provided herein. Upon
termination of this Agreement, each party shall pay to the other party that portion of
compensation specified in this Agreement that is earned and unpaid prior to the effective date of
termination.
Moffatt & Nichol Engineers
October 2006 Page 6
19. COMPLIANCES:
Consultant shall comply with all state or federal laws and all ordinances, rules and
regulations enacted or issued by ARRA.
20. CONFLICT OF LAW:
This Agreement shall be interpreted under, and enforced by the laws of the State of
California excepting any choice of law rules which may direct the application of laws of another
jurisdiction. The Agreement and obligations of the parties are subject to all valid laws, orders,
rules, and regulations of the authorities having jurisdiction over this Agreement (or the
successors of those authorities.)
Any suits brought pursuant to this Agreement shall be filed with the courts of the County
of Alameda, State of California.
21. ADVERTISEMENT:
Consultant shall not post, exhibit, display or allow to be posted, exhibited, displayed any
signs, advertising, show bills, lithographs, posters or cards of any kind pertaining to the services
performed under this Agreement unless prior written approval has been secured from ARRA to
do otherwise.
22. WAIVER:
A waiver by ARRA of any breach of any term, covenant, or condition contained herein
shall not be deemed to be a waiver of any subsequent breach of the same or any other term,
covenant, or condition contained herein, whether of the same or a different character.
23. INTEGRATED CONTRACT:
This Agreement represents the full and complete understanding of every kind or nature
whatsoever between the parties hereto, and all preliminary negotiations and agreements of
whatsoever kind or nature are merged herein. No verbal agreement or implied covenant shall be
held to vary the provisions hereof. Any modification of this Agreement will be effective only by
written execution signed by both ARRA and Consultant.
24. INSERTED PROVISIONS:
Each provision and clause required by law to be inserted into the Agreement shall be
deemed to be enacted herein, and the Agreement shall he read and enforced as though each were
included herein. If through mistake or otherwise, any such provision is not inserted or is not
correctly inserted, the Agreement shall be amended to make such insertion on application by
either party.
25. CAPTIONS:
The captions in this Agreement are for convenience only, are not a part of the Agreement
and in no way affect, limit or amplify the terms or provisions of this Agreement.
Moffatt c& Nickel Engineers
October. 2006 Page 7
IN WITNESS WHEREOF, the parties have caused the Agreement to be executed on the
day and year first above written.
ALAMEDA REUSE & REDEVELOPMENT
MOFFATT & NICHOL ENGINEERS AUTHORITY
By: '�-s/ n ,97 ,0_ WAS -'
Title:
Debra Kurita
Executive Director
RE OM ► D "ED FOR APPROVAL:
Leslie A.-Little
Development Services Director
Nanette Banks
Finance & Administration Manager
APPROVED AS TO FORM:
eresa Hi g Ism
City Attorney
Moffatt & Nichol Engineers
Octohcr. 2006 Page 8
MOFFATT & NICHOL
August 24, 2006
Ms. Nanette Banks
Finance & Administration Manager
Development Services Department
City of Alameda, California
950 West Wall Square
Alameda, CA 94501 -7552
2001 N. Main Street
Suite 360
Walnut Creek, California 94596
(925) 944 -5411
Fax (925) 944 -4732
Exhibit "A"
Subject: 2006 -2007 Condition Assessment of Piers 1, 2 and 3 for MARAD
M &N No. 04003 -18
Dear Ms. Banks:
Moffatt & Nichol (M &N) proposes to provide engineering services to the City of Alameda (City)
for the 2006 -2007 City Fiscal Year condition assessment of Alameda Naval Air Station Piers 1,
2 and 3 for MARAD occupancy. The work envisioned is multidiscipline and will involve the
effort of structural, civil, electrical and mechanical engineers as well as divers. Our proposed
scope of services and associated fee estimate are detailed below.
SCOPE OF WORK
M &N will provide condition assessment in conformance with MARAD's long term safe
layberthing requirements. These services are anticipated to include the following activities:
• Document Search
• Above Water Inspection
• Underwater Inspection
• Above Deck Structural Assessment
• Mooring Hardware Assessment
• Facility Assessment — Civil
• Facility Assessment — Electrical
• Facility Assessment — Mechanical
• Report
• Attend Meetings
Document Search
The first task will be document search to obtain any relevant, existing drawings or reports on
the piers. Some preliminary searches have been made to the City of Alameda drawing room
Nanette Banks, City of Alameda
August 24, 2006
Page 2
but only a limited amount of useful information was obtained. Under letter head of the City of
Alameda, Moffatt & Nichol will request drawings from Southwest Division in San Diego.
Above Water inspection
Moffatt & Nichol will visually inspect the piles (and sheet piles on Pier 1) above water,
underside of the deck and below deck utilities to assess the general condition. This work will
be done from a boat. Areas of pile or sheet pile damage will be flagged for subsequent
underwater inspection. Field sketches will be made as needed to identify damaged or
deteriorated areas and for subsequent reporting.
Underwater inspection
We propose to inspect a representative sample of the piles below water. Pier 1 is
approximately 650 feet long by 50 feet wide, Pier 2 is approximately 1,240 feet long by 80 feet
wide and Pier 3 is approximately 1,360 feet long by 150 feet wide. Piers 2 and 3 are concrete
pile supported while Pier 1 is a cellular type structure made up of sheet piles. Pier 2 has
approximately 1,000 concrete piles. Pier 3 has approximately 4,450 concrete piles (based on
the Dasse Report Dated Jan2, 1991). In additional to the concrete piles, we estimate that there
are approximately about 1,700 timber fender piles total on Piers 1, 2 and 3.
To perform an underwater inspection on all of the piles and sheet piles is a major undertaking
— on the order of 120 days of diving. We feel this level of inspection is not necessary to
establish the general condition of the piers. For the pile support piers, we propose to perform
Level 1 underwater inspection on approximately 5% of the structural concrete piles and Level
2 underwater inspection on approximately 1/2% of the structural concrete piles. Level 1
inspection is a visual / tactile inspection of the pile from the mudline to the water surface.
Level 2 inspection involves cleaning the piles at three bands — the mudline, midlevel and
splashzone as well as a strip connecting the bands. The cleaned piles are then inspected for
cracks or deterioration. For Pier 1, the sheet pile supported pier, we propose to visually
inspect the entire underwater surface and measure the steel thickness remaining at 28
locations. The fender piles are generally considered as a wear item. A number of these piles
will be difficult to inspect due to the moored vessels. We propose to perform a Level 1
inspection on approximately 10% of these piles to qualitatively establish the condition.
The proposed underwater inspection effort is summarized below:
Location
Number of Level
1 Structural
Piles
Number of Level
2 Structural
Piles
Number of Sheet
Pile Thickness
Measurements
Number of Level 1
Fender Piles
Pier 1
N.A.
N.A.
28
43
Pier 2
75
8
N.A.
52
Pier 3
200
20
N.A.
75
We propose to perform the diving using surface supplied air and hard hats. The dive team will
consist of one diver, a standby diver and a dive tender / note taker. The dive duration is
estimated at three weeks. The diver will relay information to the surface via microphone and
receivers in the helmets. The standby diver will be prepared to enter the water in the event of
C:\Documents and Settings \nbanks.000 \Local Settings \Temp\Nanetle Banks 060824.doc
Nanette Banks, City of Alameda
August 24, 2006
Page 3
a loss of communication with the diver. The divers will swap duties after 4 hours of diving.
We anticipate very limited visibility. Photographs of some representative conditions will be
taken. Moffatt & Nichol will provide the City with an underwater inspection report summarizing
our findings as part of the general assessment report described later.
In the event that the City requires an inspection all piles, we will provide a fee once drawings
are obtained and an accurate pile count determined.
Deck Structural Assessment
We will assess the structural condition of the deck by walking the deck and noting any areas of
deterioration. Based on the design drawings, the vertical load capacity of the piers will be
established and compared with MARAD requirements. In the event that drawings cannot be
located then approximate calculations will be performed based on our measurements and the
assumed conditions to determine if the pier satisfies MARAD load requirements.
Mooring Hardware Assessment
Mooring hardware will be compared with the drawings (if available) to establish their design
capacity. In the event that no drawings are available, then the mooring hardware will be
measured and compared with catalog information to deduce the probable capacities.
Hardware in poor condition will be noted and the capacity reduced appropriately.
Facility Assessment — Civil
The Potable water capacity and sewer system will be evaluated based on observed condition.
Flow rate for the potable water will be evaluated by tapping fixtures and measuring volumes.
Facility Assessment — Electrical
We understand that the City of Alameda has replaced the electrical service on piers 1 and 3
and is considering the replacement of the electrical service on pier 2. We assume electrical
plans and specifications are available. The new electrical service should not require field
condition assessment, but the plans will be compared with the MARAD requirements.
The existing electrical service on Pier 2 is old. In the event that the City elects to keep this
service in use, then Moffatt & Nichol with the assistance of a local electrical engineer will
assess the condition and adequacy for MARAD's requirements. This on Pier 2 is considered
an additive item to the scope.
Facility Assessment — Mechanical
The adequacy of the existing hydrant system will be tested to determine if it satisfies MARAD's
requirements. This work will be performed by a sub consultant.
Report
C:\Documents and Settings\nbanks.000 \Local Settings \Temp \Nanette Banks 060824.doc
Alameda Reuse and Redevelopment Authority
Interoffice Memorandum
November 1, 2006
TO: Honorable Chair and Members of the
Alameda Reuse and Redevelopment Authority
FROM: Debra Kurita, Executive Director
RE: Alameda Point Project Update
Background
On October 4, 2006, staff provided the Alameda Reuse and Redevelopment Authority (ARRA)
with a project update. The update included a chronology of negotiations with the Navy, a
summary of APCP's election to withdraw from the project and an explanation of initial next
steps. Following the presentation, the ARRA Board directed staff to initiate a Request for
Qualifications (RFQ) process to determine if there is a qualified developer interested in
assuming master developer obligations and rights pursuant to the draft conveyance term sheet
negotiated with the Navy in June.
Discussion
The RFQ for an Alameda Point Master Developer was issued on Thursday, October 19, 2006.
A press release notifying the public of the availability of the RFQ was released the same day.
The RFQ was posted on the project web site (www.alameda- point.com). The press release was
posted on the City's web site with a link to the project web site. In addition, the national
Association of Defense Communities, the base closure trade organization, published an article
about the RFQ in its October 20 newsletter.
There and will be a mandatory bidders conference on October 30th Fifteen developers have
submitted notices of Intent to Participate in the conference. Responses to the RFQ are due on
December 4, 2006. Along with their qualifications material, the developers will be obligated to
submit a non- refundable fee of $20,000 in order to be considered. Staff and an economic
consultant will evaluate the Responses to identify qualified developers to recommend to the
ARRA Board for an exclusive due diligence period to determine interest in the project. The
ARRA Board will rank the qualified developers and award the top ranked developer an
exclusive 45 -day period to further evaluate the project. During that period the selected
developer will also be expected to negotiate a 24 -month exclusive negotiation agreement
(ENA) with the ARRA. The selected developer will be required to submit a $100,000 deposit
at the time of selection by the ARRA Board. If the selected developer and ARRA do not
execute an ENA after 45 days, the selected developer will forfeit its $100,000 deposit and shall
be disqualified from proceeding further in the selection process.
Agenda Item 3 -A
11 -1 -06 ARRA
Honorable Chair and Members of the November 1, 2006
Alameda Reuse and Redevelopment Authority Page 2
If the selected developer and the ARRA execute an ENA, the developer will be required to
augment its $100,000 deposit by and additional $900,000 to achieve a total good faith deposit
of $1 million. The $1 million will be refunded to the selected developer at the execution of a
Disposition and Development Agreement (DDA). If the selected developer does not execute a
DDA with the ARRA within 24 months, the $1 Million deposit will be forfeited and the
developer will be disqualified from proceeding further. If a selected developer is disqualified .
at any time during the process, the ARRA will have the option of proceeding with the next
highest ranking qualified developer or discontinuing the process and proceeding with the Navy
through an alternate property disposal method.
ARRA staff is continuing to evaluate the viability of alternative disposal strategies, including
the existing no -cost EDC, and anticipates providing the Board with a comprehensive analysis
prior to its next meeting in December.
Fiscal Impact
It is anticipated that all costs to evaluate the developer qualifications will be covered by the
responder's $20,000 non - refundable deposits.
Recommendation
This report is for information only and no recommendation is required
Respectf t . -. emitted,
avid Brandt
Assistant City Manager
"F.
By: eIb e ' tter
Acting Alameda Point Project Manager
DB:DP:sb
Alameda Reuse and Redevelopment Authority
Interoffice Memorandum
November 1, 2006
TO: Honorable Chair and Members of the
Alameda Reuse and Redevelopment Authority
FROM: Debra Kurita, Executive Director
RE: Alameda Point Environmental Remediation Update: Western Shoreline —IR Sites 1,
2, and 32, Soil at IR Site 25 (Coast Guard North Housing), and Compliance with
Marsh Crust Ordinance
Background
At the October 4, 2006 ARRA Board meeting, several Board Members requested additional
information about specific Installation Remediation Sites (IR Sites) at Alameda Point and the Marsh
Crust Ordinance, which applies to portions of both Alameda Point and the former Fleet and
Industrial Supply Center Oakland, Alameda Facility /Alameda Annex (FISCA).
The discussion below provides an update for IR Sites 1, 2, 32, and 25. A follow -up of the reported
violation of Alameda's Marsh Crust Ordinance is also provided. A map is attached that shows the
locations of the various IR Sites.
Discussion
Western IR Sites
IR Site 1
The 78 -acre IR -1, located at the northwestern most corner of Alameda Point, includes a 14.7 -acre
landfill, which was used to dispose of most Naval Air Station wastes from 1943 until 1956.
Originally, IR -1 consisted of the approximate footprint of the landfill, but its boundaries were later
expanded to include the surrounding area encompassing all radioactivity detected during a
radiological survey.
The Navy has issued the Proposed Plan for IR Site 11 (IR -1 PP), the public comment period for
which is September 27 to November 10, 2006, with a public meeting on October 24, 2006. The
ARRA submitted written comments to the draft proposed plan on July 27, 2006 (copy attached).
ARRA's two primary comments are:
1 Proposed Plan for IR Site 1, 1943 -1956 Disposal Area, Former NAS Alameda, Navy,
September 2006.
Agenda Item 3 -B
11 -1 -06 ARRA
Honorable Chair and Members of the November 1, 2006
Alameda Reuse and Redevelopment Authority Page 2
1. The landfill should be topped with an impermeable engineered cap, rather than the water -
permeable soil cover that the Navy proposes; and
2. The proposed land use controls should not be imposed on the portions of IR -1 outside the
footprint of the landfilled wastes, because sampling has not encountered any subsurface
contamination beyond the landfill proper. Any contaminated surface soil is to be removed
by the Navy as part of the IR -1 cleanup. Once this is done, there is no known reason to
manage IR -1 land outside the landfill proper any differently than other land in the runways
area that is not part of an unclosed IR site.
The Navy did not incorporate the ARRA's comments in the IR -1 PP.
The Navy is proposing a soil cover for the landfill. However, the ARRA's environmental
consultant's assessment is that an impeuueable engineered cap would be more appropriate. This
assessment is based on the fact that the cover's primary role would be to act as a physical barrier to
isolate the buried wastes from contact by human and ecological receptors and that the soil cover
would do little to retard downward percolation of precipitation into the landfill. Such precipitation
inflow to the buried wastes could exacerbate potential contaminant migration through groundwater.
Currently, there is relatively little migration of wastes from the landfill through groundwater.
However, if such contaminant migration were to increase in the future, EPA and DTSC may require
upgrading to an impermeable engineered cap. For now, the environmental regulators have agreed to
allow the Navy to use a soil cover coupled with an intensified groundwater- monitoring program.
Unfortunately, if the soil cover ever had to be upgraded to a water - impermeable engineered cap in
the future, activities at the site, such as a possible golf course, would be severely disrupted for a
year or more.
The IR -1 PP proposes two institution controls, which are not necessary and would be a burden to
future use of the land:
• Prohibit demolition activities (including paved surfaces), unless transferees gain
regulatory and Navy approval and comply with a risk management plan.
• Restrict excavation and/or disturbance of soil in areas within the boundary of IR -1,
but outside the landfill footprint, unless transferees gain regulatory and Navy
approval and comply with a risk management plan.
The first of these institutional controls would prohibit removal of the runway pavement, even
outside the footprint of the landfill. The second institutional control causes IR -1 soil outside the
landfill to be treated differently from the rest of the runway area, even though no subsurface soil
contamination above regulatory screening levels was discovered during the remedial investigation.
Both of the institutional controls could make it more cumbersome to build and maintain a future
golf course at IR -1. Both the EPA and the DTSC agree with this ARRA comment on the draft
proposed plan. The EPA recommends that the ARRA restate its argument as a formal comment on
the final IR -1 PP, and it likely would be accommodated in drafting of the Record of Decision
(ROD).
Honorable Chair and Members of the November 1, 2006
Alameda Reuse and Redevelopment Authority Page 3
IR Site 2
IR Site 2 is a closed landfill at the southwest corner of Alameda Point and is planned for transfer
from the Navy directly to another Federal agency, such as US Fish and Wildlife Service or Veterans
Administration. Accordingly, the ARRA has no future development plans at this site that might be
affected by the nature of Navy remediation of the landfill. Given these circumstances, ARRA staff
generally does not comment on IR Site 2 activities, but monitors the Navy's activities there.
Environmental remediation activities at this site are also closely monitored by Federal and state
wildlife agencies, as well as by EPA and DTSC.
IR Site 32
The 6 -acre IR -32 is located immediately east of IR -1 along the south shore of the Oakland Inner
Harbor. The Navy stored equipment, vehicle, scrap, and aircraft on open space in the eastern portion
of the site prior to 1953. A storage and repair of underwater weapons occurred in Building 594 on
the site. There are no documented releases of hazardous materials at IR -32. The Navy removed two
underground fuel tanks in 1994. IR -32 was created to address VOCs detected in groundwater in
conjunction with removal of the tanks.
The Navy issued a draft remedial investigation report for IR Site 32 (IR -32)2 (IR -32 RI) in late
September 2006, with comments due by November 27, 2006. The IR -32 RI includes the results of
field sampling, a site - specific baseline human health risk assessment (HHRA), and a screening -level
ecological risk assessment (ERA). ARRA staff does not plan to submit comments on the IR -32 RI
based on a review of and concurrence on the document by its environmental consultant.
Following the IR -32 RI, the Navy will prepare a feasibility study to evaluate options for remediatiog
the human health risk for residential land use. In addition, the State Lands Commission, relying on
advice of the DTSC, must find that contamination remaining at the site is compatible with
Tidelands Trust uses.
Coast Guard HousinR- North
IR Site 25 Soil
The 46 -acre IR -25 includes Estuary Park, the Coast Guard Housing Management Office, and the
currently unoccupied Coast Guard North Village Housing. The Navy has issued the Proposed Plan
for IR Site 25 soil3 (IR -25 PP), the public comment period for which was August 21 through
September 20, with a public meeting on September 12, 2006. The Navy plans to issue the draft
ROD for IR -25 soil on December 20, 2006. The ROD likely will not require further soil removal by
the Navy. However, future landowners may incur costs to test for and potentially to remove
contaminated soil, especially when improved areas, such as buildings, pavement, and trees, are
2 Draft Remedial Investigation Report, IR Site 32, Northwest Ordnance Storage Area, Alameda
Point, Alameda, California, prepared by Bechtel for the Navy, September 27, 2006.
3 Proposed Plan for IR Site 25 Soil, Former NAS Alameda, Navy, August 2006.
Honorable Chair and Members of the November 1, 2006
Alameda Reuse and Redevelopment Authority Page 4
disturbed. Based on a review of the document and concurrence with the conclusions by the
ARRA's environmental consultant, ARRA did not submit written comments on the IR -25 PP.
IR -25 soil is contaminated with polynuclear aromatic hydrocarbons (PAHs), which were present in
the dredge sediments that were used to fill the marsh formerly present at the site. About 67,000
cubic yards of PAH- contaminated soil from approximately 25.6 acres of the site was excavated and
hauled away between November 2001 and September 2002. This is soil where the PAH levels were
the highest in near- surface soil in unimproved areas (areas not overlain by buildings, hardscape, or
trees). In an earlier removal effort, the Navy excavated approximately 300 cubic yards of soil to a
depth of four feet beneath Cloverleaf Park, which is located within North Village Housing.
The IR -25 PP proposes institutional controls to remedy remaining PAHs in soil. Specifically,
1. Prohibit excavation of soil from depths greater than four feet in areas that are not covered by
existing hardscape unless future landowner gains regulatory and Navy approval of, and
complies with, a soil management plan (SMP). EPA and DTSC will require the future
landowner to enter into an enforceable agreement for building removal and major site work.
2. Require the future landowner to gain written approval from the regulatory agencies and the
Navy and comply with a SMP before the demolition or removal of hardscape, buildings, and
structures (e.g., concrete roadways, parking lots, foundations, sidewalks) existing at the time
of ROD issuance. EPA and DTSC will require the future landowner to enter into an
enforceable agreement for building removal and major site work.
Future property owners, not the Navy, will be responsible for the costs of remediating PAHs in soil
in improved areas, when the buildings, hardscape, or trees are removed.
It is anticipated that DTSC will require additional assurances regarding PAH concentrations in soil
prior to development of this site. For example:
• Bringing in additional soil, which may be in conjunction with construction needs
(for example, surcharging), creating four feet of clean soil separation between
residences and dredge fill;
• Collecting additional samples from each individual lot to ensure that the PAH
concentration is not locally excessive; and/or
• Additional excavation if an acceptable average PAH concentration is not
achieved for each lot.
Groundwater contamination at IR -25, primarily benzene and naphthalene, is being addressed
separately from the soil contamination. The draft ROD for IR -25 groundwater was issued for
regulatory agency review on September 8, 2006.
Marsh Crust Ordinance
The Marsh Crust Ordinance (City of Alameda Ordinance 2824, February 15, 2000) is one of several
institutional controls used to avoid potential human health risk from contact with marsh crust
contaminants. The ordinance requires that a permit be obtained from the Alameda Chief Building
Honorable Chair and Members of the November 1, 2006
Alameda Reuse and Redevelopment Authority Page 5
Official before excavating to depths at which marsh crust might be encountered.4 A member of the
Alameda Point RAB stated at a recent RAB meeting he has observed excavation operations
conducted without a necessary permit pursuant to the Marsh Crust Ordinance. The City contacted
the RAB member directly for additional details, but he had no specific information regarding any
violations of the Marsh Crust Ordinance.
The Navy recently completed a five -year review of remedies implemented for marsh crust,
including the Marsh Crust Ordinance.5 The review process included interviews with persons
involved with implementation of the Marsh Crust Ordinance. The Catellus interviewee noted that
Catellus routinely asks the City of Alameda for permits before excavating into the marsh crust.
None of the interviewees mentioned any violations of the Marsh Crust Ordinance. The Navy's five -
year review includes the following finding:
"No significant problems or concerns regarding the implementation of land use controls for
the marsh crust and the former subtidal area materials underlying FISCA and Alameda Point
over the past five years were identified during the interviews."
Recommendation
This report is for information only and no recommendation is required.
espectf
David Brandt
Assist ..t City Ma ger
By: D •ie Pott -r
Acting Alameda Point Project Manager
DB:DP:sb
Attachments: Map of IR Sites
ARRA's Comment Letter on IR -1 PP
4 "No permit shall be required...for excavation associated with emergency repair of public
infrastructure facilities; provided, however, that soil excavated from below the threshold
depth...must be managed as though it were hazardous...." Marsh Crust Ordinance 13- 56.4.b.
5 Final Report, First Statutory Five -Year Review of Remedies Implemented for Part I —PCB and
Cadmium Impacted Shallow Soils, Installation Restoration Site 02(IR02), Fleet and Industrial
Supply Center Oakland, Alameda Facility /Alameda Annex (FISCA) and Part II —Marsh Crust at
Fleet and Industrial Supply Center Oakland, Alameda Facility /Alameda Annex (FISCA), and
Marsh Crust and Former Subtida/ Area at Alameda Point, Alameda, California, prepared by CDM
for the Navy, April 28, 2006.
6 three representatives from the City of Alameda, three from the Navy, one from the DTSC,
one from the FISCA RAB, and one from Catellus
" "-WV.ci
r3i , CERCLA SITE BOUNDARY
/414,..?
///*.....'')''-' ' ..- -7"...':-*4,,,,.......
.:-.z., ..,- Al4Raoii, ED DISPOSAL PARCEL
EDC-13
+,K—N, — EDC-14 EDC - Economic Development
/ Conveyance
WESTERN 14 EDC-16
8AYSIDE 15 FED - Federal Transfer
- , PBC-1B —_ _ _
(29 '
f--- .. PBC - Public Benefit Conveyance
:..,. ,...... EDC-20 (FED-4)
/ ,----, TERM - Reverts to City
\\Ili - _
-
FISC - Special Legislation
,_, _ 35
) , ......
-' .-
i . ...:
I - -- -- - -, \ \
--.- — SURVEY (EBS) PARCEL
----,„ E:1 OPERABLE UNIT 1
. I I
i i J. :- 1 OPERABLE UNIT 2A
, i
i i _
-"1,71:-
, 1 r—i OPERABLE UNIT 28
ik I FED-2C I 1 1
'
...". • I 1 OPERABLE UNIT 2C
1 F E D 2 A , 5 \
i \
, -...., ''' -1-
FED-1A ----------- 26 • -
,,.....___-_,- I -
,t,,I1
,
I ; 1 .
5 , , ■ I
/ OPERABLE UNIT 3
OPERABLE
: -L-. , _ _ , _ __ _ pC_21 (FED-3) 1, _ , ee..4 OPERABLE UNIT 4A
i E.,.. 2 : P (-1 , I
-- ,---,1 1 i OPERABLE UNIT 48
\ .
*„.", , \ 1 EDC-15
LEIZj f , EDC-6
\ is E DC- 9
,
, ' ' - 7 1 i OPERABLE UNIT 4C
-
. 1 I OPERABLE UNIT 5
_
4, ,0 i
.11----'----'--- -------A-- \ `-.1 ... ..___ J ' s< 1 ' 1 1 OPERABLE UNIT 8
-----.--Ak ,,
) - ----L.:TS_ , f - ' ' ' EDC 4 -6
S'17 BUILDING
,., aoca _ _
, ND COVER LA
----. _ _ — t FT
f--1 OPEN WATER
- 21
4 ' i ._, ,_. ,-,,,..!
Eno 2 , • 11 ND:
, I - - 1:7.74 CERCLA .. Comprehensive Environmental -
, , . .
&EAR ,I I , GOON , ,,,,,,r,(a.F.!-- F Response, Compensation. and
SfrE d DESCRIPTION SAN t - , 19 : ,,,. c t--- tJablity Act of 1980
22 '
, i 9411956 DISP., MEA , I ED C A ,1
2 WEST SEAC.11 LANDFILL MG ASSCCIATE0 riETLANOS FRANCISCO
- 9"- _±,i.j..* 1
EDC-10
3 ABANDONED FUEL STORAGE AREA
4 BUILIANS 360 (AIRCRAFT ENGINE FAcung BAY ' 27 1 1
5 13011.10150 $ (AIRCRAFT R0250116 FACILITY) - J 1 ' I
( ,
0 SIRLOINS 41 (ANICRAFT INTERMEDIATE MARITENANGE _
FACILITY) r n
1 1 / N
7 13211.61142 45a (NAVY EXCHANGE SERVICE STATION) - 1 _ 23
'1 i:I INF
a ammo 114 (PESTICIDE STORAGE AREA)
9 BUILDING 410 (PAINT STRIPPING FAGILMO FED-1B - - w
10 BUILDING 403 (MSSILE II MORN OPERATIONS) 24 FEJC-12 )' 4.,_,4__-_,
II SUILIDINS 14 (ENGINE TEST cELI.)
17 BUILDING 10 (POWER PLANT) w • .
• ' .1 all,.., I 6
13 FORMER olL REFINERY i . 600 0 600 1200 Feat
14 FORMER FIRE TRAINING AREA • . 1... =W. IP — .P!!1
_
15 SUILOINGs 301 MO See DORMER TRANSFORMER STORAGE AREA) - - - - -------..t-.".• ' EDC-11
10 C-2 CANS AREA (58177e212 cONTAINER 51120131)
I 77 SEAPLANE LAGOON 1 '''' ' S. " 1.C".
1 19 YARD 013 (FIAZARDO US WkSTE STMSOR) EDC-18B Suffech
20 OAKLAND INNER HARBOR
21 BUILDING 102 (SHIP FITTING AND ENGINE REPAIR)
22 EUND040 547 (FoRNER SERVICE STATION)
23 IMILDING 530 (MISSILE REWORK OPERATION11 - ....., : 1 EDC-17
' 77-',... r----
,t
BREAKWATER BEACH , ,,, - I ...
Alameda Point
I24 PIER 1 ANO 2 SEOMENTS
23 EZTuARY PARR ONO 7. coAST SUMO HOUSING ARE, TERM-1 1 Department of the Navy, BRAG 15540 Wed, San Dego, CaleornIa
29NESTERN HMSAR ZONE
I r DOCK ZONE ,
126 TOM SHIPYARD '
25 SKEET RANCE OPERABLE UNITS, CERCLA SITES
, 30 MILLER SCH..
I 31 MARINA VILLAGE AND DISPOSAL PARCELS
32 NORTHWESTERN oRONANCE STORAGE AREA
33 SOUTH TARNAc ARO RUNwAY WETLANDS EDC-IIIA I
I 34 FORMER NORTinnEsT sHop AREA
35 ViEST HOUSING AREA
- -
Ile..
laxamaattuavuxunusztlaa:ari=v4:i4m:z-:1
:',,i;;IPAillgiriliqo 11:iiblili r:Fa
1 fla;;013-1gELITE1 ' __ !HP!!!irtt.
ci4,103.q.gAiI.E4 ,„ ;;041! iiihN3 '
iflr ° hiiiiTiligi H141 IYEtP
i'VJ2 V.4;;11. 1,1.71g; .10,1
1-4 1 lig 1 IP lii ili,
1 1 Iii i i 141 PO
4 - V
1
July 27, 2006
City of Alameda California
Mr. Thomas L. Macchiarella
BRAG Environmental Coordinator
Navy BRAC Program Management Office
1455 Frazee Road, Suite 900
San Diego, CA 92108-4310
Re: Comments on May 15, 2006 Draft Proposed Plan for IR Site 1, 1943-
1956 Disposal Area, Former NAS Alameda
-ritArY""4--
Dear Mr,>0.aectliarella:
Thank you for the opportunity to comment on the Navy's May 15, 2006 Draft
Proposed Plan for IR Site 1, 1943-1956 Disposal Area, Former NAS Alameda
(PP). Although the original comment period for this draft document has
passed, the Alameda Reuse and Redevelopment Authority (ARRA)
understands that the Navy has yet to finalize the PP due to its continuing
discussions with environmental regulators. The ARRA offers the following
comments.
GENERAL COMMENTS
1. The PP should disclose that the Navy has not conducted sampling and
analysis to characterize subsurface soil in IR Site 1, including the
landfill contents. The Navy's IR Site 1 investigation strategy contrasts
with its approach in other IR Site remedial investigations at Alameda
Point. Without such disclosure, the public likely will assume the Navy
has formulated and selected the remedial alternatives based on
thorough knowledge of subsurface conditions. Public comments might
urge a more conservative remedial alternative for Area 1 (the landfill
proper), if the public were aware of the uncertainty surrounding
subsurface conditions.
Oevelopment Services Department
950 West Mall Square
Alameda, California 94501-7552
510.749.5800 • Fax 510.749.5808 • TD[) 510.522.7538
Attachment 2
Agenda Item #3-B
11-1-06 ARRA
(,)Printed on Recycled Paper
Mr. Thomas L. Macchiarella
July 27, 2006
Pg. 2 of 4
In contrast, the lack of subsurface characterization deprives
decisionmakers and public commenters of a basis for deciding whether
subsurface remediation, including institutional controls, is appropriate
in areas other than Area 1. Currently, there is no documentation of
subsurface soil contamination in these areas. None of the soil samples
from deeper than two feet bgs (below ground surface) in IR Site 1
(other than in Area 1) exceed any USEPA PRGs (Preliminary
Remediation Goals). Potentially overly protective institutional controls
should not be a substitute for a thorough remedial investigation.
Remedial Alternatives S2-3 (a preferred alternative), S2-4, S3-4 (a
preferred alternative), S5-4 (a preferred alternative), S5-5, and S5-6
are examples of this issue. These alternatives generally require
institutional controls restricting contact with subsurface soils, even
after the Navy remediates the surface soil, despite the absence of
documentation that subsurface soils are contaminated. Imposing the
burden of institution controls on land that does not require
remediation would not be a cost-effective remedy.
2. The PP should more accurately state the implications of IR Site l's
Tidelands Trust status. IR Site 1 is entirely within the Tidelands Trust,
which is administered by the State Lands Commission (SLC). Tidelands
Trust status restricts and uses to those that are water-related—for
example, water-related commerce, navigation, fishing, habitat
conservation, bathing, swimming, boating, general recreational
purposes, and visitor-serving facilities, such as restaurants, hotels,
shops, and parking areas. The SLC requires remediation of IR Site 1 to
support Tidelands Trust uses. The SLC likely will look to the DTSC for
guidance about whether the level of remediation at IR Site 1, including
institutional controls, is appropriate for such uses.
3. As stated in ARRA's comments on earlier IR Site 1 documents, the
ARRA believes the Navy should install an engineered cap, rather than a
soil cover, over the landfilled waste. This conclusion derives from the
uncertainty that a soil cover will be effective into the future, coupled
with the severe disruption of golf course operations that would occur if
the Navy installs an engineered cap due to remedy failure after
Alameda builds the golf course.
SPECIFIC COMMENTS
1. Remedial Investigation and Prior Feasibility Studies and Removal
Action Summary (p. 3) The text should disclose that the Navy has not
characterized subsurface conditions in the landfill footprint through
Mr. Thomas L. Macchiarella
July 27, 2006
Pg. 3 of 4
sampling and analysis, except for Area lb. The Navy has collected and
analyzed eight soil samples from Area 3 from below 2 feet bgs and
three soil samples from Area 5. Although the Navy analyzed these
samples for a wide suite of analytes, none of the results exceeds the
USEPA PRGs. No soil samples from deeper than 2 feet bgs were
analyzed from Areas 2 or 4.
2. Remedial Action Objectives (p. 6, left column, middle) The text
states: "IR Site 1 is within the boundary of the public trust land at
Alameda Point, which may not be used for general purpose industrial,
retail, or commercial space; offices; or housing." It is ambiguous
whether "general purpose" refers to retail and commercial space as
well as industrial space. Further, offices would be an allowed use,
provided they support water-related activities. A more accurate
wording of this sentence would be "IR Site 1 is within the boundary of
the public trust land at Alameda Point, which must be used for
activities that are water-related—for example, water-related
commerce, navigation, fishing, habitat conservation, bathing,
swimming, boating, general recreational purposes, and visitor-serving
facilities, such as restaurants, hotels, shops, and parking areas."
(changed portions are emphasized)
3. Preferred Alternatives, Alternative S1-4a for Soil Area 1 (p. 15, right
column, middle). The text should not overstate the certainty of long-
term effectiveness of this remedial alternative for Area 1 (the landfill
proper). The text states the following is a key point upon which the
Navy bases its preference for this alternative: "Permanently removes
some contamination and prevents further migration of remaining
contamination." Because the Navy has not characterized subsurface
conditions in Area la, it is uncertain that the remaining wastes, which
may include buried drums, will not migrate in the future. A more
accurate way of formulating this sentence might be: "Permanently
removes some contamination and helps prevent further migration of
remaining contamination." (changed portion is emphasized)
Thank you for considering the ARRA's comments. If you have any questions
or need additional information, please contact me or Peter Russell at (415)
492-0540.
Sincerely,
r
bie Potter
Base Reuse and Community Development Manager
AGENDA
Special Meeting of the Governing Body of the
Alameda Reuse and Redevelopment Authority
* * * * * * **
Alameda City Hall
Council Chamber, Room 390
2263 Santa Clara Avenue
Alameda, CA 94501
1. ROLL CALL
2. CONSENT CALENDAR
Wednesday, November 21, 2006
Meeting will begin at 7:31 p.m.
Consent Calendar items are considered routine and will be enacted, approved or adopted by one motion unless a
request for removal for discussion or explanation is received from the Board or a member of the public.
2 -A. Approval of 2 -year lease with 3 one -year options with Makani Power for Building 19.
3. REGULAR AGENDA ITEMS
None.
4. ORAL COMMUNICATIONS, NON - AGENDA (PUBLIC COMMENT)
(Any person may address the governing body in regard to any matter over which the
governing body has jurisdiction that is not on the agenda.)
5. COMMUNICATIONS FROM THE GOVERNING BODY
6. ADJOURNMENT
This meeting will be cablecast live on channel 15.
Notes:
• Sign language interpreters will be available on request. Please contact the ARRA Secretary at 749 -5800 at
least 72 hours before the meeting to request an interpreter.
■ Accessible seating for persons with disabilities (including those using wheelchairs) is available.
■ Minutes of the meeting are available in enlarged print.
■ Audio tapes of the meeting are available for review at the ARRA offices upon request.
Alameda Reuse and Redevelopment Authority
Interoffice Memorandum
November 21, 2006
TO: Honorable Chair and Members of the
Alameda Reuse and Redevelopment Authority
FROM: Debra Kurita, Executive Director
SUBJ: Approve a 2 -year lease with 3 one -year options with Makani Power for
Buildingl9
Background
At the October 2006 ARRA meeting, the ARRA approved a five one -year option lease
with Makani Power $242,640 annually or $1.15 per sq foot for the building and $0.35 per
sq foot for the shed. Makani Power is an alternative energy company that will use
Building 19 and the associated shed for office and some light manufacturing of their
product.
Since the approval of the lease, Makani has asked for qualified shell improvements to
ensure the building remains safe from water intrusion and enable them to comply with the
maintenance service requirements of the lease. Building 19 is the former airport control
tower, which is in good condition since being renovated in 1999. A map of Building 19
is attached.
Discussion
While Building 19 is in general good condition, there are some maintenance issues with
the building that were not addressed in the 1999 renovation. Staff is recommending a
$150,000 qualified shell improvement credit to be amortized over the initial 2 -year period
of the lease ($6,250 /month). In the first year, the new rental income will be $167,640
($75,000 less). In addition to the shell credit, the ARRA will use a portion of its existing
roof contingency budget to perform repairs to the building.
Fiscal Impact
The Makani lease represents new revenue to the ARRA, not included in the lease revenue
projection for fiscal year 2006 -07. The projected revenue of $242,640 will be adjusted
for the shell credit to $167,640, with annual 3% increases.
Recommendation
It is recommended that the Alameda Reuse and Redevelopment Authority approve the 2-
year lease with 3 one -year options with Makani Power for Building 19.
Honorable Chair and Members of the November 21, 2006
Alameda Reuse and Redevelopment Authority Page 2
DK/LAL/NB:dc
Attachments: Map of Building 19
Respectfully submitted,
Leslie Little
Development Services Director
By: anette Bai
Finance & Administration Manager
LJ