2009-12-02 Joint CC ARRA CIC MinutesMINUTES OF THE SPECIAL JOINT CITY COUNCIL,
ALAMEDA REUSE AND REDEVELOPMENT AUTHORITY (ARRA)
AND COMMUNITY IMPROVEMENT COMMISSION (CIC) MEETING
WEDNESDAY- -DECEMBER 2, 2009- -7:01 P.M.
Mayor/Chair Johnson convened the Joint Meeting at 8:09 p.m.
ROLL CALL - Present: Councilmembers / Board Members /
Commissioners deHaan, Gilmore, Matarrese,
Tam and Mayor/Chair Johnson – 5.
Absent: None.
MINUTES
(09-494 CC/09-54 CIC) Minutes of the Special Joint City Council and
CIC Meeting held on November 17, 2009. Approved.
Vice Mayor/Commissioner deHaan moved approval of the Minutes.
Councilmember/Commissioner Tam made a correction to page 1.
Councilmember/Commissioner Tam seconded the motion, which carried
by unanimous voice vote – 5.
REGULAR AGENDA ITEM
(09-55 CIC) Update on Alameda Landing
The Economic Development Director gave a brief presentation.
Chair Johnson inquired whether the second amendment to the
Disposition and Development Agreement (DDA) has been adopted, to
which the Economic Development Director responded in the
affirmative.
Commissioner Matarrese inquired whether the Commission has an $8
million obligation to Catellus because they bought the [Stargell]
right-of-way.
The Economic Development Director responded that is correct if
Catellus does not move forward with the project; the amount would
be slightly less because a small retail parcel was included.
Commissioner Matarrese requested a table with all of the details;
stated the Commission is spending money that Catellus is obligated
to reimburse; a ledger should be prepared showing the balance of
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
1
the reimbursements on both sides; $2 million was spent on the
hospital that burned down; all future updates should show the
balance on both sides.
The Economic Development Director continued the presentation.
Chair Johnson inquired what Catellus is supposed to be doing now.
The Economic Development Director responded Catellus is supposed to
be moving forward with the project; stated milestones provide
outside deadlines; new design review is needed for the alternative
first phase; continued the presentation.
Chair Johnson requested information on the number of people
employed for the Stargell project.
Commissioner Tam stated $3 million was borrowed from the Sewer Fund
because Catellus was not able to provide the match for the STIP;
inquired how the amount would be repaid.
The Economic Development Director responded lease revenues from the
Fleet Industrial Supply Center (FISC) budget; stated a minimum of
$90,000 has to be repaid each year; however, the plan is to repay
the full amount in five years.
Commissioner Tam stated that she was asking about the Sewer Fund
because letters have been received about rat infestations at
Alameda Point; there have been sewer overflow issues; that she is
concerned about repayment in the event a major repair is needed.
The Economic Development Director stated lease revenues from ARRA
cover Alameda Point; funds are separate.
The Interim Executive Director stated there are questions about
whether the rat infestation is the ARRA portion of the sewer or
somewhere else; the matter could be addressed later; the loan was
done because staff felt it was important to protect STIP funding;
the Public Works Director would address the Sewer Fund at a later
time.
Commissioner Matarrese stated the CIC has to repay the Sewer Fund;
inquired whether CIC funds are vulnerable to State taking, to which
the Economic Development Director responded in the affirmative;
stated FISC funds would be used first.
Commissioner Matarrese inquired whether repaying the loan would
help keep the funds from the State, to which the Interim Executive
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
2
Director responded it is the opposite; the State cannot take debt.
The Economic Development Director stated the payment to the State
is from tax increment money, which is not being used to repay the
Sewer Fund.
Commissioner Matarrese stated the loan should be repaid if the line
gets crossed at some point and the debt is not worth carrying.
The Economic Development Director stated the State structured the
statutes so that agencies with debt are not obligated to make
payment; however, the General Fund can make the payments; agencies
are shut down until payments are made.
Commissioner Matarrese stated the issue could be addressed in an
Off Agenda Report.
Commissioner Tam inquired whether the entire redevelopment agency
is shut down [in the event of non-payment].
The Economic Development Director responded the States shuts down
agencies administratively; stated only up to 75% of the previous
year administration costs can be spent; bonds and new projects are
not allowed; limited housing can be done; continued the
presentation.
Chair Johnson inquired whether the whole hospital structure is
gone, to which the Economic Development Director responded not
completely.
Chair Johnson inquired whether removing the building after the fire
was more costly, to which the Economic Development Director
responded Catellus bids show demolishing the building before the
fire would have been less expensive.
Chair Johnson inquired whether an investigation was conducted
regarding whether the Fire Department let the building burn and if
so, what were the results.
The Interim Executive Director responded that she would find out
and provide information.
Commissioner deHaan stated a report was supposed to come back.
Chair Johnson stated the fire ended up costing a lot of money.
The Economic Development Director stated costs escalated when the
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
3
material burned because hazardous material mixed with non-hazardous
material.
Commissioner deHaan inquired whether the costs of fighting the fire
and monitoring the site are included in the $2.2 million, to which
the Economic Development responded the cost is the contract cost
and does not include Fire Department costs.
Commissioner deHaan questioned whether including the costs of
fighting the fire would be appropriate; stated that he believes so
because Catellus was tasked with demolishing the building and
neglect caused it to end up being burned; various loans have been
provided; inquired whether all loans have payback agreements.
The Economic Development Director responded in the affirmative;
stated there are promissory notes.
Commissioner deHaan inquired about the duration of loans and
whether loans have interest, to which the Economic Development
Director responded the sewer loan has interest; stated that she
does not believe the loan from the ARRA to the CIC has interest but
the loan is to be paid back from the first developer proceeds.
Commissioner deHaan stated the ledger has two sides; Catellus
putting up $8 million is commendable; the other side of the ledger
has $5.2 million; the delta is closing; the last update in March
indicated there has been no activity for six months; nine months
later there has been no activity, except City activity; inquired
what oversight the City has to hold the developer’s feet to the
fire.
Chair Johnson stated the question goes back to what the developer
is supposed to be doing now.
The Economic Development Director responded the developer is
supposed to be facilitating a first phase prior to the outside
deadline of 2012.
Chair Johnson inquired whether specific things are required.
Commissioner deHaan inquired whether there is not a take down
requirement.
The Economic Development Director responded in the negative; stated
the developer does not have to take down any property until after
the 2012 period; pre-conditions to taking down property, including
plans and engineering, have to be done to facilitate the transfer
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
4
of the property and start of construction; by 2012, all of those
things need to be done or the developer needs to inform the
Commission that they will not be moving forward with a project.
Commissioner Matarrese inquired whether all the things that need to
be done to take down the property need to be done by 2012 and
whether there is a list of the items, to which the Economic
Development Director responded in the affirmative; stated
entitlement actions have to be in place; the developer is coming
back with a schedule and wants to work towards having construction
start within the next 18 months to two years; to do so, plans would
have to be submitted by January or February of next year.
Commissioner Matarrese inquired whether the developer would meet
the schedule, to which the Economic Development Director stated the
developer is working very hard with a key tenant to come forward
with a project.
In response to Chair Johnson’s inquiry about what would be
presented to the Planning Board in January or February, the
Economic Development Director stated a new design review permit
would be needed.
Chair Johnson stated demolition and backbone have to be done by
2012; inquired whether the developer would be in default if they
are not ready to go by December 2012.
The Economic Development Director responded in the affirmative;
stated take down is not required for a couple of years after.
Chair Johnson inquired whether anything between now and 2012 would
cause the developer to be in default, to which the Economic
Development Director responded in the negative.
Commissioner deHaan stated the developer is land banking because of
the market.
The Economic Development Director stated consideration was given
because Catellus provided money for [Stargell] right-of-way
acquisition; being ready for construction will take 18 to 24
months; old infrastructure needs to be ripped out and new
infrastructure needs to be installed.
Commissioner Matarrese stated that he appreciates the investment of
$8 million for the right-of-way, which is also for Alameda Point,
not just Alameda Landing; something got done; the College got a
laboratory; 2012 is not far away; that he wants to hear what is
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
5
being done to meet the deadline; the City should be thinking about
a Plan B if things are not on track and the milestone is not met.
The Economic Development Director stated alternative strategies
include interim leasing in two warehouses.
In response to Chair Johnson’s inquiry about interim leasing, the
Economic Development Director stated the minimum lease time would
need to be three years to cover rewiring costs.
Commissioner Matarrese stated negotiations could be done if the
prospect is that the [2012] deadline might not be met; that he
wants to hear from Catellus about what is occurring.
Chair Johnson stated the interim leasing improvements could be
amortized in three years; the demolition and backbone will take two
more years; the project is phased; interim leasing could be done;
the frustration is nothing is being done; that she understands the
economy; the City appreciates the $8 million to get Stargell done;
the perception is nothing is being done.
Commissioner Gilmore stated Catellus stepped up and facilitated
Stargell; the City is not out trying to attract tenants; getting
financing is very difficult; banks are not lending and are sitting
on cash waiting for the commercial real estate market implosion;
that she understands the frustration and feels it; however, the
developer is trying to bring in a tenant in the worst market since
the depression.
Mayor Johnson stated Catellus obtained the project entitlement
during the good economy; stated that she is anxious to hear what is
being done; inquired what year Catellus received entitlement.
The Economic Development Director responded the original DDA was
approved in 2000; the project was bifurcated in 2003 to allow
Bayport to go forward; re-entitlement was not done until 2006.
Chair Johnson inquired what year the Exclusive Negotiation
Agreement (ENA) was done.
The Economic Development Director responded that she does not have
the history; stated that she heard there was not a lot of interest
in the property.
Commissioner deHaan stated five developers were boiled down to
three and all were substantial companies capable of completing the
project.
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
6
The Economic Development Director stated the 2003 changes
recognized the office market was gone.
Chair Johnson stated housing would not be built right now because
houses would not sell even if financing could be secured.
The Economic Development Director stated half of the potential
tenants from one year ago do not exist.
Sean Whiskeman, Vice President of Retail Operations for Catellus,
gave a brief presentation on the history of the company and
project; stated Catellus has a signed letter of intent with Target
and is in active negotiations with several other retailers;
Catellus is in a position to justify a project that is quite a bit
larger than the project that went through the community and staff;
the City’s [2004] Retail Study put the project on hold; Catellus
has not been sitting idle; the real [investment] number is close to
$20 million, including entitlement money, designs and plans,
without any return.
Chair Johnson stated the City has been involved in the steps; not a
lot has happened in the past couple of years.
Mr. Whiskeman stated it is a new market; the rules changed
September 2008; retailers have put expansion plans on hold, filed
bankruptcy or liquidated; Catellus has to have a tenant in order to
justify the construction expense; building cannot be done on a
speculative basis; discussed the Target negotiations and deal;
stated Catellus hopes to commence the process in early 2010 and is
excited about discussions with a potential second anchor.
Chair Johnson stated the fundamental question is whether Catellus
will be able to meet the first performance milestones.
Mr. Whiskeman stated Catellus is very aware of the timeframes,
believes milestones can be met and is reviewing commencing the
first residential phase, which would have a significant lead up;
Catellus is trying to advance aspects other than just retail.
Chair Johnson inquired whether the demolition and backbone
conditions would be met by December 2012, to which Mr. Whiskeman
responded in the affirmative; stated Catellus could even be ahead
of schedule.
Chair Johnson inquired whether something would be submitted to the
Planning Board in January or February.
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
7
Mr. Whiskeman responded in the negative; stated the process would
start; the site plan works but needs to be revisited; starting in
early 2010, Catellus would work with staff to build the package and
address issues.
Chair Johnson stated the Commission needs to hear whether or not
the project will move forward; Catellus should not plan on land
banking; her intent is not to allow the land to sit.
Mr. Whiskeman stated dialog with staff would continue; nothing will
sneak up on anyone; that he is making a presentation to the West
Alameda Business Association (WABA); Catellus has supported WABA
events and pledged money to the Miracle League.
Chair Johnson stated more frequent reports would help the
Commission understand the status.
Mr. Whiskeman stated that he would be happy to do so; one of the
DDA commitments is to meet with the City Manager’s office once a
quarter, which has been done.
Chair Johnson inquired whether the leasing discussed is for
existing structures, to which Mr. Whiskeman in the negative.
Commissioner Matarrese stated the quarterly meetings should be
official reports to allow the Commission to hear directly from the
developer.
Mr. Whiskeman noted names [of potential tenants] would not be
discussed in public.
Commissioner Matarrese stated that he wants to hear about
activities; the Commission needs to be informed if the project is
dead in order to start formulating decisions that would need to be
made in the event the milestone is not met.
Chair Johnson inquired whether the December 2012 decision point
would be whether the project would go forward as scheduled or if
there would be an extension or adjustment of the milestones, to
which Mr. Whiskeman responded Catellus should know long before
[December 2012].
Chair Johnson inquired when Catellus would have a good sense of
whether Target wants to come to Alameda.
Mr. Whiskeman stated Catellus has a good sense that Target wants to
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
8
come to Alameda now; it is the beginning of a long process;
Catellus will work towards needed approvals to meet the projected
opening date.
Chair Johnson inquired what is the opening date.
Mr. Whiskeman responded the date is in flex right now, but is
before December 2012.
Commissioner deHaan stated when Catellus was bought out, it was six
to eight months before decisions were made about the company
continuing to do development; in the past, not too many acres were
going to be given to Target; the staff report indicates Target
would now have 10 acres and be sprawling; inquired whether Catellus
is contemplating selling off that much property.
Mr. Whiskeman stated the project would be one of Target’s smaller
stores and would be around 130,000 square feet.
Commissioner deHaan inquired how much parking would be required, to
which Mr. Whiskeman responded right now the project includes the
City maximum of 4 spaces per 1,000 square feet.
In response to Commissioner deHaan’s inquiry, Mr. Whiskeman stated
Target prefers to be part of a shopping center, but does do stand
alone stores; noted guidelines setting maintenance standards would
be recorded against the property.
Commissioner deHaan inquired whether Catellus anticipates
developing the shoreline.
Mr. Whiskeman responded Catellus has an interest; stated there are
restrictions; the largest available land use is commercial/office;
amenities will be out near the waterfront; other land uses are
being considered, such as senior housing.
Commissioner deHaan inquired whether longer-term leases could be
done to span the time.
Mr. Whiskeman responded Catellus is open to cooperating; stated
many buildings are generating revenues.
Commissioner Tam stated Catellus has been in various negotiations
in the past including Clif Bar and Target; requested that Mr.
Whiskeman elaborate on lessons learned; inquired whether Target
terminated a previous letter of intent.
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
9
Mr. Whiskeman responded that he was not involved with Clif Bar
negotiations; stated the site and building could not be delivered
in a time frame that worked for Clif Bar; the first time around
with Target, the City made a decision to take a collective time out
to do the Retail Study; analysis took time.
Chair Johnson stated the City is fortunate office buildings were
not constructed because they would have been empty; Towne Centre
would have been half empty if Catellus had gone forward with the
retail; buildings would be empty if the City had been more
aggressive.
Commissioner deHaan noted that the City of Alameda did everything
possible to move the Clif Bar project forward.
Mr. Whiskeman stated Catellus underestimated what it would take to
deliver the site to Clif Bar.
Chair Johnson stated Clif Bar was concerned about being in the area
alone; other businesses would not commit to locate at the site.
Commissioner Tam stated Catellus has holdings in other Bay Area
locations; inquired whether getting a planned development to move
forward in Alameda is more difficult than other cities.
Mr. Whiskeman responded the 1.1 million square foot project in
Fremont was a different experience because the site is not near
residential and there was a lot of City and community support.
Chair Johnson stated projects get sidetracked, such as the gas
station at Towne Centre; the process needs to be streamlined and
should not take so long.
Mr. Whiskeman noted it costs money when approvals take a long time.
Commissioner Tam stated community members are concerned that there
should be a way to control the mix or types of stores that go into
a retail development; people want stores similar to Emeryville;
inquired how high end stores make decisions about where to locate
and whether said stores would go in next to a Target.
Mr. Whiskeman responded the City is an Island with a primary trade
area that can only rely on Alameda, which is almost always not
enough; high end retailers end up in communities with a greater
draw; provided examples; stated there are exceptions.
Commissioner Matarrese stated limitations are understood, but the
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
10
project needs to be sold.
In response to Chair Johnson’s inquiry regarding retail leakage,
Mr. Whiskeman stated Target has been trying to locate in Alameda
for ten years.
Chair Johnson stated the City needs to be ready to proceed when
Target is ready.
Commissioner deHaan noted Bridgeside did not live up to
expectations; stated Catellus is required to inform the City about
the type of businesses that will be built.
Mr. Whiskeman stated the retail industry has changed; disposable
dollars have evaporated; the way people shop is changing.
In response to Chair Johnson’s inquiry about current leakage
numbers, Commissioner Tam stated the 2006 leakage report shows the
City loses $0.74 of every $1.00.
Commissioner Matarrese stated quarterly updates are important to
ensure months do not go by without addressing where things are
going and the Commission can help manage the process and set
priorities; an objectionable project will not go forward because
times are tough; the Commission will not let Target slip through
the City’s fingers.
Chair Johnson stated standards should be set in advance for
businesses trying to locate in Alameda; the City’s procedures need
to be set so locating in Alameda is not a multi-year process.
Commissioner Gilmore stated the Commission looks forward to
Catellus returning in three months time for additional discussions;
public, developer and tenants expectations need to be managed for
development projects; the City’s task going forward is to let
everyone know how long the process takes and what is possible.
Commissioner Matarrese stated Target should be mindful of the
City’s past discussions on labor, big box and parking requirements;
the laundry lists should be revisited; the City needs to clear the
way and ensure people understand what is coming.
Mr. Whiskeman stated people in the industry might be willing to
come to the quarterly updates to provide additional information.
COUNCIL REFERRAL
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
11
(09-495 CC/ARRA/09-56 CIC) Discussion of Policies for Leases at the
ARRA and Tidelands Leases under the City’s Jurisdiction.
Councilmember/Board Member/Commissioner Matarrese made the referral
because it dovetails on earlier discussions regarding the maritime
industry in Alameda. He would like to have the Council/ARRA/CIC
provide direction to the Interim City Manager to look at leasing
policies and consider a few points: 1) look at terms of leases and
the City’s ability to have longer term leases with the goal of
building a business community and a business sector out at Alameda
Point that will be the future commercial occupants, so that the
developer does not says there is no market for commercial at
entitlement; 2) because we are an island and have a great seaside
location, there need to be review of what can be done to support
and make-healthy marine-related industries, whether it is ship
building or the private boat sector, which throws off a significant
amount of sales tax; 3) also look at protecting the waterfront – a
lot of installations are on tidelands where there is potential for
someone else to maintain the bulkheads and the shore side
investments. The key issue is creating a leasing policy to grow a
diverse commercial sector and not a monolithic commercial sector;
leasing strategies should include a diverse economic base to take
advantage of potential, such as maritime industry, a growing
specialty foods industry, a wine and distillation industry,
entertainment production, and a potential for green businesses. If
marketed correctly and the City can get some relief from the Navy
on the provision of unilateral termination of leases, in order to
build the sector that is going to be the future commercial tenants;
risk will be spread in economic downtimes and benefit to the City
will be maximized that will also relieve over-reliance on
residential property taxes. He would like to get direction on
giving these points to the City Manager and looking at revising
lease policies that go back to 2007.
Councilmember/Board Member/Commissioner Gilmore stated that if the
Council/Board/CIC decides that this is a good idea, changes should
not be done in a vacuum. One of the items pulled from the agenda
the other night was a long-term lease with WETA. The WETA lease
should be analyzed in the context of whatever new policies are
created, because that could very well be the template for moving
forward as WETA will be a major tenant out there for a very long
period of time. How the City deals with WETA could very well set
the stage for how the City deals with any other industries. It is
something in hand now, is not something being theoretically talked
about, and is also a maritime industry.
Councilmember/Board Member/Commissioner Matarrese added that WETA
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
12
is trailing $20 million that they want to plant on the shoreline.
His main point is that templating leases was tried before. There
are some speakers that can talk specifically about some of the
unique facets of the private marine industry; WETA is a public
agency with a different guarantee of revenue than the private
sector. The City has to diversify and look at policies not in a
template, but against goals; some goals may not be revenue-
participation as mentioned in 2007, but may be more investments in
the land side structure to keep the bulkheads intact so that the
Island does not slide into the water, or to maintain the berths, or
to bring jobs, or to generate sales tax. Opening with a set of
goals to attract and establish desirable businesses and industry at
Alameda Point, have diversity rather than a monolithic, single
sector-driven development, which could be the future of commercial
development; when entitlement happens, the developer does not come
back to tell the City that they have to build more houses because
there is no commercial market. The City should build its own
market, look at the issue comprehensively and set up a flexible
policy, more goal-driven, and not narrow.
Mayor/Chair Johnson clarified that there is no current leasing
policy in place except for de facto policy; potential tenants go
through a lengthy and delayed process and eventually give up.
The Interim City Manager stated that one of the ways to tackle the
issue, because it is comprehensive, rather than wait 90–120 days
for a paper with a huge narrative, is to engage in dialogue.
Suggested the issue be placed as an item on the ARRA meeting in
February and a discussion start with a City Manager presentation of
a working outline that deals with policy parameters, financial
issues, users, the major big categories; then take Council’s
thoughts, incorporate them, have dialogue and get reactions to the
working draft outline before staff starts crafting language and
finds out it is going in a totally different direction than the
Council wants to go. A comprehensive asset management policy and
strategy will take months to draw up, so before staff starts off in
one direction, let’s get a working outline, make sure we are on the
right track in terms of business points, and then it is easier to
go back and deal with the language.
Mayor/Chair Johnson called the speakers: Andy McKinley, General
Manager and Harbor Master of Grand Marina, expressed his support in
working with the City to maximize the income from the marine
industry. He provided the Board with a copy of a letter regarding
an economic threat (permit) by the State Water Resources Control
Board.
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
13
Bill Elliot, Bay, Ship & Yacht Company President expressed his
concern about the two owners (Alameda Gateway and the City) of the
property which Bay Ship & Yacht occupies; that they are in
litigation, which puts their business in an unsuitable situation.
He wants to work with the City to draw up a lease, which is
mutually beneficial to all parties.
Mayor/Chair Johnson recommended that a more appropriate approach
for Mr. Elliot to discuss this issue is to set up a meeting with
staff, as the larger impediment is the litigation.
The Interim City Manager agreed and stated that it is a strategic
issue and is best that the Council has an opportunity to discuss
the issue in Closed Session and get an update from the City
Attorney as to the status of the litigation, and to see what role,
if any, the Council and staff can deal with in terms of the
strategy with respect to the litigation and how it can positively
impact Bay Ship & Yacht. As the Mayor stated, the issue needs to
be carefully discussed inside so as not to compromise either side.
Bob Henn, Bay Ship & Yacht, also supports having a dialogue with
the City. The Assistant City Attorney committed to calling Mr.
Henn to discuss the issue without possibly jeopardizing any
confidential settlement communications.
Leslie Cameron, Owner of Bay Ship & Yacht, supports a continued
relationship between the City and Bay Ship & Yacht and stated some
key points: Bay Ship & Yacht provides $90,000 to $110,000 sales tax
dollars per year, has spent $17 million on its facility, pays over
$100,000 per year in property taxes, spent $600,000 in Alameda this
year, and is actively involved in many community projects. Bay Ship
& Yacht currently employs 250 people. Ms. Cameron expressed that
she appreciates the support of the City.
Councilmember/Board Member/Commission Tam made statements to
understand and clarify the discussion. She stated that the issue
of Bay Ship & Yacht and the revision of the guidelines are separate
matters. She further stated that Councilmember/Board Member/
Commissioner Matarrese has submitted a request to revise the
policies for leases at Alameda Point.
The Interim City Manager suggested a fuller discussion at the next
ARRA meeting be held to try to understand expectations and develop
an asset management strategy.
The Council/ARRA/CIC agreed with Councilmember/Board Member/
Commissioner Tam’s statements and agreed with the Interim City
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
14
Manager’s recommendation to itemize the issue to discuss and create
a working draft outline at the next ARRA meeting in February.
ADJOURNMENT
There being no further business, Mayor/Chair Johnson adjourned the
Joint Meeting at 11:04 p.m.
Respectfully submitted,
Lara Weisiger, City Clerk
Secretary, CIC
Irma Glidden
Secretary, ARRA
The agenda for this meeting was posted in accordance with the Brown
Act.
Special Joint Meeting Alameda City Council, Alameda
Reuse and Redevelopment Authority and Community Improvement Commission
December 2, 2009
15